From: Tim on 25 Mar 2010 03:36 Hi All, i have a question on how i can setup a task so that it will span over 10 days worth of duration (eg we have a 10 day lead time for change request to be reviewed. It takes about an hour to raise the change). I still want to show the duration of 10 days. If i use the work and duration columns sure it works but if you go into the resource usage view, it spans the work out in effort over the whole duration. If i want the 1 hour of work to be done on a particular day, how do i change this? Thanks in advance
From: Jan De Messemaeker on 25 Mar 2010 04:41 Hi, Make the task fixed duration In one of the usage views, write 1h as work in the day you want the work to halppen, 0 for the other days. Hope this helps, -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Tim" <Tim(a)discussions.microsoft.com> wrote in message news:CF7A4414-6215-4B2F-A241-465AD7227C53(a)microsoft.com... > Hi All, > > i have a question on how i can setup a task so that it will span over 10 > days worth of duration (eg we have a 10 day lead time for change request > to > be reviewed. It takes about an hour to raise the change). > > I still want to show the duration of 10 days. If i use the work and > duration columns sure it works but if you go into the resource usage view, > it > spans the work out in effort over the whole duration. If i want the 1 > hour > of work to be done on a particular day, how do i change this? > > Thanks in advance
From: "Steve House" sjhouse at hotmail dot on 25 Mar 2010 19:04 I suggest you reconsider your approach, especially since you want the resource to work on the task as a unit. Once he starts it will take him and hour to finish and there's a 10 day window during which he needs to get it done. If he's going to give it his full attention for that one hour, it's a 1 hour duration task. It has a deadline 10 days after he receives it but that 10 day window is not its duration. Consider for a moment what happens if he jumps right on it the moment it hits his desk and gets it done an hour later. If you have set it up as a 10 day duration task with one hour of work, it's going to sit in limbo for the next 9 days, needlessly delaying the rest of the project until that 10 days has expired because according to the project plan, it won't be finished until 10 days after it really has been finished. Better to model physical reality... a 1-hour duration task that is able to start any time after XX date and with a completion deadline of no later than 10 days later. -- Steve House MS Project Trainer & Consultant "Tim" <Tim(a)discussions.microsoft.com> wrote in message news:CF7A4414-6215-4B2F-A241-465AD7227C53(a)microsoft.com... > Hi All, > > i have a question on how i can setup a task so that it will span over 10 > days worth of duration (eg we have a 10 day lead time for change request > to > be reviewed. It takes about an hour to raise the change). > > I still want to show the duration of 10 days. If i use the work and > duration columns sure it works but if you go into the resource usage view, > it > spans the work out in effort over the whole duration. If i want the 1 > hour > of work to be done on a particular day, how do i change this? > > Thanks in advance
|
Pages: 1 Prev: Gantt View shading Next: Integration to Dynamics GP |