From: G�rard Ducouret on 10 Nov 2009 08:31 morfeus, First, check the start date of your project in Project / Project Information Second : you can specify the range of dates while printing in the Print dialog : From... to... Hope this helps, G�rard Ducouret "morfeus" <morfeus(a)discussions.microsoft.com> a �crit dans le message de news: D857BFD0-42DE-40BC-9032-B7FE9134BB32(a)microsoft.com... >I just made a project with a few entries starting in january 2010. When > printing the gantt I'm getting the november and december 2009 columns on > the > print too, even though there is no entries in this period. Anyways, I > want > to decide what part of the diagram I want to print, preferable with a > starting and ending date, no matter where the actual data is.
|