From: Gary D on 4 Jun 2010 03:30 I would like to set week numbers on a programme from a specific date of my choosing rather than project start or end or from fiscal or calendar year dates. Is this possible -- GDD
From: Rob Schneider on 4 Jun 2010 06:56 As far as I know, there is no way to change how the week numbers are computed. However, what you could do is implement your own algorithm for computing week number based on date using one of the custom number fields. --rms www.rmschneider.com On 04/06/10 08:30, Gary D wrote: > I would like to set week numbers on a programme from a specific date of my > choosing rather than project start or end or from fiscal or calendar year > dates. Is this possible
From: Jan De Messemaeker on 4 Jun 2010 07:02 Hi, Block the start date of the starting task(s) then set Project Start (in Project menu, Project information) to the start of your week counting -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Gary D" <GaryD(a)discussions.microsoft.com> wrote in message news:306705D6-1519-475D-94E0-D57463D21DC3(a)microsoft.com... >I would like to set week numbers on a programme from a specific date of my > choosing rather than project start or end or from fiscal or calendar year > dates. Is this possible > -- > GDD
|
Pages: 1 Prev: Importing .xml file into Microsoft Project 2007 Next: Resource Groups |