From: Paddy on
I need help on how to schedule the following in MS Project 2003, prof
edition. Thanks in advance for your help

I have 3 tasks to schedule.

Task 1 - Total work 2 days - Work will be done 0.5 days each day (AM
sessions) and will end after 4th day by lunch
Task 2 - Total work 1.5 days - Work will be done 0.5 days each day (PM
sessions) and will end after 3rd day by lunch

Task 3 - Total work 1 day - Work will be done 0.5 days each day will start
after task 2 is complete (on the 4th day).
From: Dale Howard [MVP] on
Paddy --

Task 1 -- Set the Duration to 4 days. Assign the resource to work 50% Units
on the task.

Task 2 -- Set the Duration to 3 days. Assign the resource to work 50% Units
on the task.

Task 3 -- Link this task to Task 2 with a Finish to Start dependency. Set
the Duration to 2 days. Assign the resource to work 50% Units on the task.

Hope this helps.

--
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


"Paddy" <Paddy(a)discussions.microsoft.com> wrote in message
news:F0DBF400-D047-4D1E-801A-7ECDBD2A4963(a)microsoft.com...
> I need help on how to schedule the following in MS Project 2003, prof
> edition. Thanks in advance for your help
>
> I have 3 tasks to schedule.
>
> Task 1 - Total work 2 days - Work will be done 0.5 days each day (AM
> sessions) and will end after 4th day by lunch
> Task 2 - Total work 1.5 days - Work will be done 0.5 days each day (PM
> sessions) and will end after 3rd day by lunch
>
> Task 3 - Total work 1 day - Work will be done 0.5 days each day will start
> after task 2 is complete (on the 4th day).