From: Paddy on 19 Apr 2010 12:55 I need help on how to schedule the following in MS Project 2003, prof edition. Thanks in advance for your help I have 3 tasks to schedule. Task 1 - Total work 2 days - Work will be done 0.5 days each day (AM sessions) and will end after 4th day by lunch Task 2 - Total work 1.5 days - Work will be done 0.5 days each day (PM sessions) and will end after 3rd day by lunch Task 3 - Total work 1 day - Work will be done 0.5 days each day will start after task 2 is complete (on the 4th day).
From: Dale Howard [MVP] on 19 Apr 2010 13:37 Paddy -- Task 1 -- Set the Duration to 4 days. Assign the resource to work 50% Units on the task. Task 2 -- Set the Duration to 3 days. Assign the resource to work 50% Units on the task. Task 3 -- Link this task to Task 2 with a Finish to Start dependency. Set the Duration to 2 days. Assign the resource to work 50% Units on the task. Hope this helps. -- Dale A. Howard [MVP] VP of Educational Services msProjectExperts http://www.msprojectexperts.com http://www.projectserverexperts.com "We write the books on Project Server" "Paddy" <Paddy(a)discussions.microsoft.com> wrote in message news:F0DBF400-D047-4D1E-801A-7ECDBD2A4963(a)microsoft.com... > I need help on how to schedule the following in MS Project 2003, prof > edition. Thanks in advance for your help > > I have 3 tasks to schedule. > > Task 1 - Total work 2 days - Work will be done 0.5 days each day (AM > sessions) and will end after 4th day by lunch > Task 2 - Total work 1.5 days - Work will be done 0.5 days each day (PM > sessions) and will end after 3rd day by lunch > > Task 3 - Total work 1 day - Work will be done 0.5 days each day will start > after task 2 is complete (on the 4th day).
|
Pages: 1 Prev: Red, Yellow, Green Status Next: PWA Queue Monitoring |