From: Jimmy D on

Hi,

Hope somebody can help me out (and I can explain what I want clearly):

We have a situation here where we have to do all test on 2 new equal
lines in our company. Line one has priority in starting up, but we have
2 teams and we want team 1 who is cheking task 1 op CP1 to also do tast
1 on CP2.

I'll try to give an example

There are 2 computers (CP1 and CP2) and 2 working teams (Team 1 and
Team 2).

Team 1 starts Task1 on CP1 (eg 5 days)
Team 2 starts Task2 on CP2 (eg 10 days)
As soon as Team1/Task1 on CP1 is finished

Team 2 starts task2 on CP1 (eg 10 days) --> Task2 on CP2 is put on
hold
Team 1 starts task 3 on CP2 (eg 10 days)
As soon as Team2/Task2 on CP1 is finished

Team 1 starts Task 3 on CP1
Team 2 _resume_ with Task 2 on CP2 ermaining 5 days

So as you can see a certain task should be put on hold as long as
another hasn't finished, and then this task should be resumed.


Is something like this possible with MSP?

Thanks,

Jimmy


--
Jimmy D
------------------------------------------------------------------------
Jimmy D's Profile: http://forums.techarena.in/members/154117.htm
View this thread: http://forums.techarena.in/microsoft-project/1270221.htm

http://forums.techarena.in

From: JulieS on
Hi Jimmy D,

I'm not sure I follow 100%, but if I understand you correctly, yes.

Create the links to drive the sequences:
In CP1:
Task 1 is the predecessor to Task 2
Task 2 is the predecessor to Task 3.

Set the priorities of the tasks in CP1 higher than the tasks in CP2.
Assign Team 2 to both Task 2 in CP1 and CP2. Team 2 will be
overallocated during the second week when Task 2 in Cp1 overlaps
with Task 2 on Cp2.

Then use resource leveling with Priority, Standard set as the
leveling order. Allow the tasks to split. Task 2 in Cp2 will be
split after 5 days, Task 2 in Cp1 will be scheduled at the split.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

"Jimmy D" <Jimmy.D.41j9rb(a)DoNotSpam.com> wrote in message
news:Jimmy.D.41j9rb(a)DoNotSpam.com...
>
> Hi,
>
> Hope somebody can help me out (and I can explain what I want
> clearly):
>
> We have a situation here where we have to do all test on 2 new
> equal
> lines in our company. Line one has priority in starting up, but we
> have
> 2 teams and we want team 1 who is cheking task 1 op CP1 to also do
> tast
> 1 on CP2.
>
> I'll try to give an example
>
> There are 2 computers (CP1 and CP2) and 2 working teams (Team 1
> and
> Team 2).
>
> Team 1 starts Task1 on CP1 (eg 5 days)
> Team 2 starts Task2 on CP2 (eg 10 days)
> As soon as Team1/Task1 on CP1 is finished
>
> Team 2 starts task2 on CP1 (eg 10 days) --> Task2 on CP2 is put on
> hold
> Team 1 starts task 3 on CP2 (eg 10 days)
> As soon as Team2/Task2 on CP1 is finished
>
> Team 1 starts Task 3 on CP1
> Team 2 _resume_ with Task 2 on CP2 ermaining 5 days
>
> So as you can see a certain task should be put on hold as long as
> another hasn't finished, and then this task should be resumed.
>
>
> Is something like this possible with MSP?
>
> Thanks,
>
> Jimmy
>
>
> --
> Jimmy D
> ------------------------------------------------------------------------
> Jimmy D's Profile: http://forums.techarena.in/members/154117.htm
> View this thread:
> http://forums.techarena.in/microsoft-project/1270221.htm
>
> http://forums.techarena.in
>


From: Jimmy D on

Yes, that did it!

Thank you so much for your help Julie!!

Jimmy


--
Jimmy D
------------------------------------------------------------------------
Jimmy D's Profile: http://forums.techarena.in/members/154117.htm
View this thread: http://forums.techarena.in/microsoft-project/1270221.htm

http://forums.techarena.in

From: JulieS on
You're most welcome Jimmy, and thanks for the feedback.

Julie
"Jimmy D" <Jimmy.D.41qg3b(a)DoNotSpam.com> wrote in message
news:Jimmy.D.41qg3b(a)DoNotSpam.com...
>
> Yes, that did it!
>
> Thank you so much for your help Julie!!
>