From: Stacey S. on 28 Jan 2010 12:38 The project plan uses fixed work tasks with the resource unit entered as the second factor. With that in mind, I wouldn't want to manually enter a duration to make the ? go away. [Project 2007] "Steve House" wrote: > Adding a bit to Mike's comment, the question mark has no real affect on > anythign going on in Project, it's simply a reminder that you haven't yet > considered what the duration of that task will likely be and you should > provide an estimate at some point before finalizing the plan. Ot > -- > Steve House [Project MVP] > MS Project Trainer & Consultant > Visit http://www.mvps.org/project/faqs.htm for the FAQs > her than serving as a reminder it has no other function or effect. > > "Phrozenbuns" <phrozenbuns(a)gmail.com> wrote in message > news:461BC4CC-9E2D-48A2-9DAD-30F78E359096(a)microsoft.com... > > ,When I add a new Task the default duration is automatically added with a > > question mark (?) How do I get rid of this question mark? Do I need to > > change > > the default settings? If So How? > > > > Phrozenbuns. > >
From: JulieS on 28 Jan 2010 12:43 Hello Stacey, No. Project will calculate the duration based upon the amount of work and the assignment unit. The ? will still appear even after the calculation of duration. To remove the ? from all tasks go to Tools > Options, Schedule tab and clear the checks from: "Show that tasks have estimate durations" and "New tasks have estimated durations." I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 1/28/2010 12:38 PM, Stacey S. wrote: > The project plan uses fixed work tasks with the resource unit entered as the > second factor. With that in mind, I wouldn't want to manually enter a > duration to make the ? go away. [Project 2007] > > "Steve House" wrote: > >> Adding a bit to Mike's comment, the question mark has no real affect on >> anythign going on in Project, it's simply a reminder that you haven't yet >> considered what the duration of that task will likely be and you should >> provide an estimate at some point before finalizing the plan. Ot >> -- >> Steve House [Project MVP] >> MS Project Trainer& Consultant >> Visit http://www.mvps.org/project/faqs.htm for the FAQs >> her than serving as a reminder it has no other function or effect. >> >> "Phrozenbuns"<phrozenbuns(a)gmail.com> wrote in message >> news:461BC4CC-9E2D-48A2-9DAD-30F78E359096(a)microsoft.com... >>> ,When I add a new Task the default duration is automatically added with a >>> question mark (?) How do I get rid of this question mark? Do I need to >>> change >>> the default settings? If So How? >>> >>> Phrozenbuns. >> >>
|
Pages: 1 Prev: MS Project 2003 Clarity Integration Next: Import Assignments Using Excel |