From: Barry Gregory Barry on 13 May 2010 10:41 What would cause a task to delay its start from its predecessor if there is no lag and no resource contention. I have 2, 3day tasks for a resource that are not lined up back to back. The second is waiting three days to start. And yes, I have a new version of project that is not completely set up to my liking.
From: John on 13 May 2010 11:34 In article <6587DA82-E174-4F1E-847D-72FFD508658D(a)microsoft.com>, Barry Gregory <Barry Gregory(a)discussions.microsoft.com> wrote: > What would cause a task to delay its start from its predecessor if there is > no lag and no resource contention. I have 2, 3day tasks for a resource that > are not lined up back to back. The second is waiting three days to start. > > And yes, I have a new version of project that is not completely set up to my > liking. Barry, My first guess is that the task is constrained with a "start-no-earlier-than". This happens if the person who entered the task manually entered a start date. You should also check the working time calendar to make sure the 3 day delay are really working days (e.g. a weekend and a Friday or Monday holiday). By the way, which version of Project are you using and which updates are installed? John Project MVP
From: Jack Dahlgren MVP on 13 May 2010 12:18 If you have a link to the summary task it can cause this. Leveling may be another cause. -Jack Dahlgren "Barry Gregory" <Barry Gregory(a)discussions.microsoft.com> wrote in message news:6587DA82-E174-4F1E-847D-72FFD508658D(a)microsoft.com... > What would cause a task to delay its start from its predecessor if there > is > no lag and no resource contention. I have 2, 3day tasks for a resource > that > are not lined up back to back. The second is waiting three days to start. > > And yes, I have a new version of project that is not completely set up to > my > liking.
From: Barry Gregory on 13 May 2010 12:50 Your thoughts are right on but I refrain from constraints so there are none and the the calendar is wide open with a normal work week. I am using Project 2007. What makes me curious is I imported this project from a book on gaming. All the resources were Material at first. Hopefully that information might help. "John" wrote: > In article <6587DA82-E174-4F1E-847D-72FFD508658D(a)microsoft.com>, > Barry Gregory <Barry Gregory(a)discussions.microsoft.com> wrote: > > > What would cause a task to delay its start from its predecessor if there is > > no lag and no resource contention. I have 2, 3day tasks for a resource that > > are not lined up back to back. The second is waiting three days to start. > > > > And yes, I have a new version of project that is not completely set up to my > > liking. > > Barry, > My first guess is that the task is constrained with a > "start-no-earlier-than". This happens if the person who entered the task > manually entered a start date. > > You should also check the working time calendar to make sure the 3 day > delay are really working days (e.g. a weekend and a Friday or Monday > holiday). > > By the way, which version of Project are you using and which updates are > installed? > > John > Project MVP > . >
From: John on 13 May 2010 13:53 In article <3660CCFD-8338-4A83-AFF2-9AB0CB4E5B5F(a)microsoft.com>, Barry Gregory <BarryGregory(a)discussions.microsoft.com> wrote: > Your thoughts are right on but I refrain from constraints so there are none > and the the calendar is wide open with a normal work week. I am using > Project 2007. What makes me curious is I imported this project from a book > on gaming. All the resources were Material at first. Hopefully that > information might help. Barry, Jack offered a couple other suggestions. Have you checked those out? If neither of those items apply it might be easier to e-mail me the file and I'll take a look. If you decide to do that, zip the file and send it to me at the address below. I will ask a few questions. John Project MVP jensenljatatfastmaildotdotfm (remove obvious redundancies) > > "John" wrote: > > > In article <6587DA82-E174-4F1E-847D-72FFD508658D(a)microsoft.com>, > > Barry Gregory <Barry Gregory(a)discussions.microsoft.com> wrote: > > > > > What would cause a task to delay its start from its predecessor if there > > > is > > > no lag and no resource contention. I have 2, 3day tasks for a resource > > > that > > > are not lined up back to back. The second is waiting three days to > > > start. > > > > > > And yes, I have a new version of project that is not completely set up to > > > my > > > liking. > > > > Barry, > > My first guess is that the task is constrained with a > > "start-no-earlier-than". This happens if the person who entered the task > > manually entered a start date. > > > > You should also check the working time calendar to make sure the 3 day > > delay are really working days (e.g. a weekend and a Friday or Monday > > holiday). > > > > By the way, which version of Project are you using and which updates are > > installed? > > > > John > > Project MVP > > . > >
|
Next
|
Last
Pages: 1 2 Prev: wrap text Next: how do i get tasks to move out days as they become past due? |