From: Abhijit on 4 May 2010 02:04 Hi, We have discovered a strange problem in MSProject after installing SP2 The task duration changes when MPP file is saved as XML and XML file is reopened. This is causing a havoc. There is nothing specific about the file. File with even one task shows the problem. Any help possible. Can I upload the file somehwere?
From: Rod Gill on 4 May 2010 04:40 Hi, I'm running Project 2007 SP2. I created 7 tasks with durations from 1d to 7d and linked them. Saved to xml. Closed. Create new project from xml file and finish date of 7th task was same and all durations same. What's the minimum you have to do to create problem? -- Rod Gill Microsoft MVP for Project - http://www.project-systems.co.nz Author of the only book on Project VBA, see: http://www.projectvbabook.com "Abhijit" <Abhijit(a)discussions.microsoft.com> wrote in message news:CD5AAF8D-BBCE-4488-AB71-1B1F59D0AEC1(a)microsoft.com... > Hi, > > We have discovered a strange problem in MSProject after installing SP2 > > The task duration changes when MPP file is saved as XML and XML file is > reopened. This is causing a havoc. > > There is nothing specific about the file. File with even one task shows > the > problem. > > Any help possible. Can I upload the file somehwere? > > __________ Information from ESET Smart Security, version of virus > signature database 5083 (20100503) __________ > > The message was checked by ESET Smart Security. > > http://www.eset.com > > > __________ Information from ESET Smart Security, version of virus signature database 5083 (20100503) __________ The message was checked by ESET Smart Security. http://www.eset.com
|
Pages: 1 Prev: Repeating Project Tasks Next: Merging different project |