From: Ms Project Noob on 12 Apr 2010 21:00 Why does MS Project set Early Finish = Finish on a project file calculated from the Project Finish for tasks in progress with float? Before the task is started the early finish is correct, when progress is taken early where actual start is before start, the task splits and early finish=finish. Why? I expected early finish to be pushed ASAP. |