From: PatB123 on
I have one task with a duration of 30 minutes. For some reason its task bar
is very short (shorter than 30minutes if viewing the timescale). However, if
I increase the task duration to 31 minutes then it correctly displays in the
window.

I"ve checked the tasks before and after it and have no unusual constraints
as far as I can tell. Any ideas as to what might be wrong? Thanks.
From: JulieS on
Hello PatB123,

Does the task show correct start and end times in the table?

My observation with Project 2007 is that the 30 min bar is actually
proportionately too long -- not too short. Does changing the bar
rounding (Format > Layout)seem to make a difference?

What version (including service pack) do you have installed?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 2/8/2010 4:10 PM, PatB123 wrote:
> I have one task with a duration of 30 minutes. For some reason its task bar
> is very short (shorter than 30minutes if viewing the timescale). However, if
> I increase the task duration to 31 minutes then it correctly displays in the
> window.
>
> I"ve checked the tasks before and after it and have no unusual constraints
> as far as I can tell. Any ideas as to what might be wrong? Thanks.