From: PatB123 on 8 Feb 2010 16:10 I have one task with a duration of 30 minutes. For some reason its task bar is very short (shorter than 30minutes if viewing the timescale). However, if I increase the task duration to 31 minutes then it correctly displays in the window. I"ve checked the tasks before and after it and have no unusual constraints as far as I can tell. Any ideas as to what might be wrong? Thanks.
From: JulieS on 8 Feb 2010 16:41 Hello PatB123, Does the task show correct start and end times in the table? My observation with Project 2007 is that the 30 min bar is actually proportionately too long -- not too short. Does changing the bar rounding (Format > Layout)seem to make a difference? What version (including service pack) do you have installed? I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 2/8/2010 4:10 PM, PatB123 wrote: > I have one task with a duration of 30 minutes. For some reason its task bar > is very short (shorter than 30minutes if viewing the timescale). However, if > I increase the task duration to 31 minutes then it correctly displays in the > window. > > I"ve checked the tasks before and after it and have no unusual constraints > as far as I can tell. Any ideas as to what might be wrong? Thanks.
|
Pages: 1 Prev: macro to count all tasks (no sumary or milestones) in a project Next: Task Updates for all Projects |