From: Derekl001 on
Can the remaining costs be shown timephased from the Status Date onwards ?
Kind regards,
Derek


"R.Scott Fleming" wrote:

> Thanks Rod, I seemed to have missed the obvious...The schedule requires
> input to manage the work to date (updating %complete or actual hours) and
> then updating the remaining work to the correct dates (ie. work goind forward
> from current date)
>
> I appreciate your help!!!
>
> "Rod Gill" wrote:
>
> > Yes, the Cost Field is the remaining cost for all dates in the future as
> > there shouldn't be any completed work in the future (it should all be moved
> > back in time to when it was actually done).
> >
> > --
> >
> > Rod Gill
> > Microsoft MVP for Project
> >
> > Author of the only book on Project VBA, see:
> > http://www.projectvbabook.com
> >
> >
> >
> > "R.Scott Fleming" <RScottFleming(a)discussions.microsoft.com> wrote in message
> > news:5A558890-DA56-4B57-9A92-42E84AE9324E(a)microsoft.com...
> > > Is there a way to see the remaining cost of a task as it is distributed
> > > over
> > > the remaining duration of the task. I would like to see this information
> > > while in the task or resource usage view.
> >
> >
From: R.Scott Fleming on
I believe the only way this can be done is to move the unfinished portion of
the task to the status date.

"Derekl001" wrote:

> Can the remaining costs be shown timephased from the Status Date onwards ?
> Kind regards,
> Derek
>
>
> "R.Scott Fleming" wrote:
>
> > Thanks Rod, I seemed to have missed the obvious...The schedule requires
> > input to manage the work to date (updating %complete or actual hours) and
> > then updating the remaining work to the correct dates (ie. work goind forward
> > from current date)
> >
> > I appreciate your help!!!
> >
> > "Rod Gill" wrote:
> >
> > > Yes, the Cost Field is the remaining cost for all dates in the future as
> > > there shouldn't be any completed work in the future (it should all be moved
> > > back in time to when it was actually done).
> > >
> > > --
> > >
> > > Rod Gill
> > > Microsoft MVP for Project
> > >
> > > Author of the only book on Project VBA, see:
> > > http://www.projectvbabook.com
> > >
> > >
> > >
> > > "R.Scott Fleming" <RScottFleming(a)discussions.microsoft.com> wrote in message
> > > news:5A558890-DA56-4B57-9A92-42E84AE9324E(a)microsoft.com...
> > > > Is there a way to see the remaining cost of a task as it is distributed
> > > > over
> > > > the remaining duration of the task. I would like to see this information
> > > > while in the task or resource usage view.
> > >
> > >