From: Derekl001 on 25 Sep 2009 11:19 Can the remaining costs be shown timephased from the Status Date onwards ? Kind regards, Derek "R.Scott Fleming" wrote: > Thanks Rod, I seemed to have missed the obvious...The schedule requires > input to manage the work to date (updating %complete or actual hours) and > then updating the remaining work to the correct dates (ie. work goind forward > from current date) > > I appreciate your help!!! > > "Rod Gill" wrote: > > > Yes, the Cost Field is the remaining cost for all dates in the future as > > there shouldn't be any completed work in the future (it should all be moved > > back in time to when it was actually done). > > > > -- > > > > Rod Gill > > Microsoft MVP for Project > > > > Author of the only book on Project VBA, see: > > http://www.projectvbabook.com > > > > > > > > "R.Scott Fleming" <RScottFleming(a)discussions.microsoft.com> wrote in message > > news:5A558890-DA56-4B57-9A92-42E84AE9324E(a)microsoft.com... > > > Is there a way to see the remaining cost of a task as it is distributed > > > over > > > the remaining duration of the task. I would like to see this information > > > while in the task or resource usage view. > > > >
From: R.Scott Fleming on 26 Sep 2009 11:17
I believe the only way this can be done is to move the unfinished portion of the task to the status date. "Derekl001" wrote: > Can the remaining costs be shown timephased from the Status Date onwards ? > Kind regards, > Derek > > > "R.Scott Fleming" wrote: > > > Thanks Rod, I seemed to have missed the obvious...The schedule requires > > input to manage the work to date (updating %complete or actual hours) and > > then updating the remaining work to the correct dates (ie. work goind forward > > from current date) > > > > I appreciate your help!!! > > > > "Rod Gill" wrote: > > > > > Yes, the Cost Field is the remaining cost for all dates in the future as > > > there shouldn't be any completed work in the future (it should all be moved > > > back in time to when it was actually done). > > > > > > -- > > > > > > Rod Gill > > > Microsoft MVP for Project > > > > > > Author of the only book on Project VBA, see: > > > http://www.projectvbabook.com > > > > > > > > > > > > "R.Scott Fleming" <RScottFleming(a)discussions.microsoft.com> wrote in message > > > news:5A558890-DA56-4B57-9A92-42E84AE9324E(a)microsoft.com... > > > > Is there a way to see the remaining cost of a task as it is distributed > > > > over > > > > the remaining duration of the task. I would like to see this information > > > > while in the task or resource usage view. > > > > > > |