From: mankoni on 24 Aug 2006 20:38 Once a project is baslined , what is the best way to handle the following scenarios ? 1) New tasks are to be added 2) Reschedule existing tasks(change start dates / dependencies) Thanks
From: Andrew Skouloudis on 25 Aug 2006 07:09 Î?/Î? mankoni(a)gmail.com ÎγÏ?αÏ?ε: > Once a project is baslined , what is the best way to handle the > following scenarios ? > > 1) New tasks are to be added > Select a task, then press the Insert button on your keyboard , a new task will be inserted before the task you had initially selected > 2) Reschedule existing tasks(change start dates / dependencies) > > To change dependencies you have to break the current dependencies.First of all select the tasks that you want to change the dependencies then go to Project Guide > Tasks > Schedule tasks and select the last image , next to the text "Click to break the link for the selected tasks " . To change start days remainig work etc go to View > Table and select Tracking, while the Gant Chart view is selected. You can see the table next to the gantt has many fields to play with. Experiment with these fields for a while and you will get the point. It's easy. Hope that helped , i am a newbie too !!!
From: mankoni on 25 Aug 2006 07:32 Andrew, Thaks for your post. What you said is the method for adding and changing task details. HOWEVER my question was how these 2 scenarios will impact the baseline and do I have to create a new baseline to track these changes ? Bascially , I want to know the impact on the baseline of these 2 actions. Thanks Andrew Skouloudis wrote: > Î?/Î? mankoni(a)gmail.com ÎγÏ?αÏ?ε: > > Once a project is baslined , what is the best way to handle the > > following scenarios ? > > > > 1) New tasks are to be added > > > > Select a task, then press the Insert button on your keyboard , a new > task will be inserted before the task you had initially selected > > > 2) Reschedule existing tasks(change start dates / dependencies) > > > > > > To change dependencies you have to break the current dependencies.First > of all select the tasks that you want to change the dependencies then > go to Project Guide > Tasks > Schedule tasks and select the last image > , next to the text "Click to break the link for the selected tasks " . > To change start days remainig work etc go to View > Table and select > Tracking, while the Gant Chart view is selected. You can see the table > next to the gantt has many fields to play with. Experiment with these > fields for a while and you will get the point. It's easy. > > Hope that helped , i am a newbie too !!!
From: Andrew Skouloudis on 25 Aug 2006 08:56 Actually when you create a baseline what you do is taking a snapshot of the current instance of the project. No matter what changes you make to your project after that, the baseline will not be modified UNLESS you want to. So adding tasks, or changing dates to tasks will not affect the baseline you had saved before , but if you want to do so , go to Project Guide > Track> Save a baseline plan to compare with later versions . See ? you have an option to update the baseline you had saved before ( adding all the changes you have made) or you can create a second baseline (MS Project 2003 can save up to 11 Baselines). Again , once a baseline is created at some point when working with your project , it wont change by itself unless you want it to change. If you want to view all the baselines you have created go to View > More Views > Multiple Baselines Gantt. Hope this helped more this time !! So, to answer your question theri Î?/Î? mankoni(a)gmail.com ÎγÏ?αÏ?ε: > Andrew, > Thaks for your post. What you said is the method for adding and > changing task details. HOWEVER my question was how these 2 scenarios > will impact the baseline and do I have to create a new baseline to > track these changes ? > > Bascially , I want to know the impact on the baseline of these 2 > actions. > > Thanks > Andrew Skouloudis wrote: > > Î?/Î? mankoni(a)gmail.com ÎγÏ?αÏ?ε: > > > Once a project is baslined , what is the best way to handle the > > > following scenarios ? > > > > > > 1) New tasks are to be added > > > > > > > Select a task, then press the Insert button on your keyboard , a new > > task will be inserted before the task you had initially selected > > > > > 2) Reschedule existing tasks(change start dates / dependencies) > > > > > > > > > > To change dependencies you have to break the current dependencies.First > > of all select the tasks that you want to change the dependencies then > > go to Project Guide > Tasks > Schedule tasks and select the last image > > , next to the text "Click to break the link for the selected tasks " . > > To change start days remainig work etc go to View > Table and select > > Tracking, while the Gant Chart view is selected. You can see the table > > next to the gantt has many fields to play with. Experiment with these > > fields for a while and you will get the point. It's easy. > > > > Hope that helped , i am a newbie too !!!
From: davegb on 25 Aug 2006 10:26 mankoni(a)gmail.com wrote: > Andrew, > Thaks for your post. What you said is the method for adding and > changing task details. HOWEVER my question was how these 2 scenarios > will impact the baseline and do I have to create a new baseline to > track these changes ? > > Bascially , I want to know the impact on the baseline of these 2 > actions. > > Thanks I think what you want is the option to save only part of the project into the Baseline. You can highlight the new task(s) and the task(s) affected by them and Save a baseling for those tasks. If you save it to the same baseline you did for the whole project, it will be added to that Baseline. Hope this helps in your world. > Andrew Skouloudis wrote: > > Î?/Î? mankoni(a)gmail.com ÎγÏ?αÏ?ε: > > > Once a project is baslined , what is the best way to handle the > > > following scenarios ? > > > > > > 1) New tasks are to be added > > > > > > > Select a task, then press the Insert button on your keyboard , a new > > task will be inserted before the task you had initially selected > > > > > 2) Reschedule existing tasks(change start dates / dependencies) > > > > > > > > > > To change dependencies you have to break the current dependencies.First > > of all select the tasks that you want to change the dependencies then > > go to Project Guide > Tasks > Schedule tasks and select the last image > > , next to the text "Click to break the link for the selected tasks " . > > To change start days remainig work etc go to View > Table and select > > Tracking, while the Gant Chart view is selected. You can see the table > > next to the gantt has many fields to play with. Experiment with these > > fields for a while and you will get the point. It's easy. > > > > Hope that helped , i am a newbie too !!!
|
Next
|
Last
Pages: 1 2 Prev: getting following error messages in project 2003 Next: Unclear error message |