Prev: SQL Server Performance Local vs Remote.
Next: Trying to get a % of responses from a survey in a query
From: --CELKO-- on 8 May 2010 14:46 >> You know the funny thing is that almost every IT project costs double what is originally quoted. I've had many clients who exclaim to me later that they wish they had held me to my quote. To which I immediately reply: in that case they would only have received what they asked for in their spec. << It is worse than that. Ever read Yourdon, Boehm, DeMarco, et al about large software projects? DeMarco's research is that 15% deliver nothing at all (cancellations, total failures), another percentage deliver nothing useful (obsolete on arrival, not up to specs, etc.) and a third percentage deliver only part of the specs. The success rate has been pretty low. I think it was Yourdon that said if we made manufactured goods the way that we make software, Henry Ford would have been bankrupt in two months. >> The reality is that we don't get specs. Certainly not detailed ones. And when I have had to complete a genuine RFT or formal quotation, I would say that initial spec would never cover more than 30% of what is eventually built. << That depends on your clients. In Defense contracting, nothing happens until you have a spec (MIL STD 2167 and its descendants); major companies that cannot have failures or "tuning time" also follow this regiment. This is a world in which we cannot say things like "there are no specs for this nuclear weapon control system, so you cowboy coders write stuff and we'll make it up as we go along." >> We now have an attitude of continual delivery and continual billing. << LOL! http://www.despair.com/consulting.html That seems to turn into continual re-coding and continual billing. Boehm's research at TRW showed that an error made in step(n) of the waterfall model cost almost exactly 10x to correct in step(n+1). Specification errors were the earliest and therefore the most expensive to correct. In fact, they were a major factor in total failures. Perhaps the most extreme example was a failed reservation system for Greyhound Bus Lines. People that ride buses pay cash at the gate; they do not make reservations. >> We agree on small milestones which they are happy to pay on. Each milestone statement is accompanied with some kind of forward estimate of work remaining but we find that the customer 'customizes' the work so much along the way that putting too much effort into a detailed spec is just pure wasteful. It is often fantasy. << When I was paid for milestones, they were well-defined (so that many teams could work in parallel), had QA tests ready to go (created by another group) and had to meet certain SEI standards. The QA suites were written from the specs without seeing any code. We had a structure chart for the whole system on the wall whose boxes showed the status of each module (uncoded, testing, approved or a traffic light). We had stub programs for the uncoded modules, so testing was possible. To get away from decades of classic research, let me do my anecdotal evidence against yours. When I was part of a team that did the Georgia State Crime Lab Database and we followed a disciplined approach, we delivered a system under budget (a first for LEAA money at the time), 4 months ahead of schedule and a system robust enough to be changed by the junior programmer on the project when we left. This made a lot of problems in a bureaucracy :) They had no way to take back money and no idea what to do with the extra man-hours.
From: Tony Rogerson on 8 May 2010 16:10 Frankly you are very industry old and in those terms stuck in the past and because folk don't employ you that often you are very out of touch and don't realise the industry has moved on considerably since the last time you did a full stretch of project work, what is it now - some 15 years ago - perhaps more? --ROGGIE-- "--CELKO--" <jcelko212(a)earthlink.net> wrote in message news:a6d97135-9e10-4a1c-aa30-ea7cb1a2fc80(a)r34g2000yqj.googlegroups.com... >>> You know the funny thing is that almost every IT project costs double >>> what is originally quoted. I've had many clients who exclaim to me later >>> that they wish they had held me to my quote. To which I immediately >>> reply: in that case they would only have received what they asked for in >>> their spec. << > > It is worse than that. Ever read Yourdon, Boehm, DeMarco, et al about > large software projects? DeMarco's research is that > 15% deliver nothing at all (cancellations, total failures), another > percentage deliver nothing useful (obsolete on arrival, not up to > specs, etc.) and a third percentage deliver only part of the specs. > The success rate has been pretty low. I think it was Yourdon that said > if we made manufactured goods the way that we make software, Henry > Ford would have been bankrupt in two months. > >>> The reality is that we don't get specs. Certainly not detailed ones. And >>> when I have had to complete a genuine RFT or formal quotation, I would >>> say that initial spec would never cover more than 30% of what is >>> eventually built. << > > That depends on your clients. In Defense contracting, nothing happens > until you have a spec (MIL STD 2167 and its descendants); major > companies that cannot have failures or "tuning time" also follow this > regiment. This is a world in which we cannot say things like "there > are no specs for this nuclear weapon control system, so you cowboy > coders write stuff and we'll make it up as we go along." > >>> We now have an attitude of continual delivery and continual billing. << > > LOL! > > http://www.despair.com/consulting.html > > That seems to turn into continual re-coding and continual billing. > Boehm's research at TRW showed that an error made in step(n) of the > waterfall model cost almost exactly 10x to correct in step(n+1). > Specification errors were the earliest and therefore the most > expensive to correct. In fact, they were a major factor in total > failures. Perhaps the most extreme example was a failed reservation > system for Greyhound Bus Lines. People that ride buses pay cash at the > gate; they do not make reservations. > >>> We agree on small milestones which they are happy to pay on. Each >>> milestone statement is accompanied with some kind of forward estimate of >>> work remaining but we find that the customer 'customizes' the work so >>> much along the way that putting too much effort into a detailed spec is >>> just pure wasteful. It is often fantasy. << > > When I was paid for milestones, they were well-defined (so that many > teams could work in parallel), had QA tests ready to go (created by > another group) and had to meet certain SEI standards. The QA suites > were written from the specs without seeing any code. > > We had a structure chart for the whole system on the wall whose boxes > showed the status of each module (uncoded, testing, approved or a > traffic light). We had stub programs for the uncoded modules, so > testing was possible. > > To get away from decades of classic research, let me do my anecdotal > evidence against yours. When I was part of a team that did the Georgia > State Crime Lab Database and we followed a disciplined approach, we > delivered a system under budget (a first for LEAA money at the time), > 4 months ahead of schedule and a system robust enough to be changed by > the junior programmer on the project when we left. > > This made a lot of problems in a bureaucracy :) They had no way to > take back money and no idea what to do with the extra man-hours. > >
From: Geoff Schaller on 8 May 2010 21:31 Joe, > It is worse than that. Ever read Yourdon, Boehm, DeMarco, et al about > large software projects? DeMarco's research is that No - which is probably the difference between the two of us. I experience these things first hand and don't need to read a book to confirm my experiences. Perhaps others wanting to get in to large firm contracting might get a picture from DeMarco but then again, you do these things because you want or it is a foot in the door. And if you're big enough to make the play, you already know the stakes... > That depends on your clients. In Defense contracting, nothing happens > until you have a spec (MIL STD 2167 and its descendants); major Oh I agree. The ONLY detailed specs and legal contracts we've had to comply with in detail came from government related work and in all cases, they should have saved the money. > >> We now have an attitude of continual delivery and continual billing. << > LOL! > http://www.despair.com/consulting.html But you don't need to read books to know that it is all about delivery of expectations you built with the client. We have found it better to agree on broad principles, set milestones and then achieve them. Get continual feedback and adjust. When they request items or changes that add to the new project cost you declare them immediately, seek approval and adjust the forward estimates. Often it is just a case of reshaping the contract and its expectations. With government contracts we get them to agree to billing points that match deliverables and then we "allow" some 15% to be withheld so that they can guarantee themselves feature completion. > That seems to turn into continual re-coding and continual billing. This is not necessarily bad and where Boehm and DeMarco fall down in their approach is that they fail to consider a genuine dynamic model for delivery. How many projects have seen the underlying technology change dramatically in the life of the project... or company aims change. Anything to be delivered over 2-3 years is going to suffer that fate. It must be factored in or all parties are going to suffer. > When I was paid for milestones, they were well-defined (so that many > teams could work in parallel), had QA tests ready to go (created by > another group) and had to meet certain SEI standards. The QA suites > were written from the specs without seeing any code. Then we aren't disagreeing. > To get away from decades of classic research, let me do my anecdotal ....oh puh-lease! Thank you :) > evidence against yours. When I was part of a team that did the Georgia > State Crime Lab Database and we followed a disciplined approach, we But this kind of project is rare. More often than not there is intervention on the part of the client that rates only as interference and other times where the contractor misunderstood a requirement and delivered it incorrectly. There need to be mechanisms to prevent both. > This made a lot of problems in a bureaucracy :) They had no way to > take back money and no idea what to do with the extra man-hours. Never had that problem. There are always ways to spend the unspent.... Especially in government. Geoff Schaller Software Objectives
From: Geoff Schaller on 8 May 2010 21:33 I laughed so hard when I saw it that I forgot to comment. In any event, "old fart" is more a term of endearment than an insult. You know... that grand pa figure in baggy pants and slippers. "TheSQLGuru" <kgboles(a)earthlink.net> wrote in message news:tamdnUhIsJTg7XjWnZ2dnUVZ_i2dnZ2d(a)earthlink.com: > > True, but at least I am not rude :) > > > That is a stunningly brash and false statement!!! > > > -- > Kevin G. Boles > Indicium Resources, Inc. > SQL Server MVP > kgboles a earthlink dt net >
From: --CELKO-- on 9 May 2010 16:30 >> where Boehm and DeMarco fall down in their approach is that they fail to consider a genuine dynamic model for delivery. << Boehm is the guy that invented the spiral development model. RAD, JAD and its Agile/Extreme descendants all go back to his work at TRW >> Never had that problem. There are always ways to spend the unspent.... Especially in government. << That was the only time I did, too :) LEAA (Law Enforcement Assistance Act) had no way to return the money. There was no account code for it. So we tried to buy expendable supplies -- not legal (that had to be State funds, not Federal). We tried to take a trip -- not legal (contract had final signatures). We tried to buy more hardware, but the HP-3000 was the largest model at the time and was in a closet so cramped it was physically impossible to add anything else. For about a year, I kept getting calls from the Feds trying to get me to spend the extra money in some creative way. We had messed up the system! The rule of thumb in the Cold War continuing contracts was to spend 105% to 110% of the year (n) budget, so you could get an increase in year (n+1). Just over enough to make it look like you were doing honest estimates, had project control, etc. and needed a little extra for the next step. Of course, a true estimate would be under as often as it is over the mark. But management also know this game and did things to control for it. When I worked for Georgia Tech, I wrote a spreadsheet to back-figure the billings we sent to the US Army each month. a year or two later, I went to work for the US Army on the other side of the campus. I was now a Contract Officer on the other side of the desk and got to reject my own spreadsheet figures. The Cold War was strange times.
First
|
Prev
|
Pages: 1 2 3 4 Prev: SQL Server Performance Local vs Remote. Next: Trying to get a % of responses from a survey in a query |