Prev: Fill colours
Next: Formulas - Test if Cell is Populated
From: Lenny on 11 May 2010 09:29 I have started a new project and have imported my WBS from excell, set my project start date, set my calender to a 10 hrs day seven days / week, outlined my phases, and am ready to schedule. The problem is that my 10 hour day is overlapping into the next day. I have had this problem in the past and cannot figure out why sometimes it happens and others it will behave like I expect. Can anyone shed some light on this?
From: Andrew Lavinsky on 11 May 2010 10:08 Could you address more specifically where you set your calendar? If you did it in Tools > Options > Calendar, then that is only partially the answer. You also have to go into Tools > Change Working Time, and modify the calendars there (or create new ones based on the 10 hour schedule) - then confirm your resources are on the same calendar. You also might go into Tools > Options and change the Date display format to include the time. That may help you assess if you have specific tasks starting midway through the day. - Andrew Lavinsky Blog: http://blogs.catapultsystems.com/epm > I have started a new project and have imported my WBS from excell, set > my project start date, set my calender to a 10 hrs day seven days / > week, outlined my phases, and am ready to schedule. The problem is > that my 10 hour day is overlapping into the next day. I have had this > problem in the past and cannot figure out why sometimes it happens and > others it will behave like I expect. Can anyone shed some light on > this? >
From: "Steve House" sjhouse at hotmail dot on 11 May 2010 10:34 Let's say your 10 hour day is 6am to 5pm with and hour for lunch. If your 1-day task starts at 6am it will finish at 5pm on the same day. But if you task starts later in the day, it will have to run over into the next day in order to be 10 hours in length. How could it start later in the day? Go to the View menu and enable a date format that includes the time. Then look at the Project Start Date. If it shows a time later than the start of your workday, all your tasks will be offset by the difference. Remember that ALL date fields are actually date/TIME fields and time is always a part of the data even when it's not being displayed. A task never simply starts on Monday; it always starts at a precise TIME on Monday and finishes at start+duration time later. -- Steve House MS Project Trainer & Consultant "Lenny" <Lenny(a)discussions.microsoft.com> wrote in message news:6EADF5CE-AE11-4D67-8964-C137BEB0DEA6(a)microsoft.com... >I have started a new project and have imported my WBS from excell, set my > project start date, set my calender to a 10 hrs day seven days / week, > outlined my phases, and am ready to schedule. The problem is that my 10 > hour > day is overlapping into the next day. I have had this problem in the past > and > cannot figure out why sometimes it happens and others it will behave like > I > expect. Can anyone shed some light on this?
|
Pages: 1 Prev: Fill colours Next: Formulas - Test if Cell is Populated |