From: ks2008 on
"Fixed Units Indicates that the task's number of assignment units must
remain constant, regardless of any change in duration or work for the task.
This is the default. For fixed-unit tasks:"

What is "assignment units" means here ?
Could you please explain ?

Thanks
KS

From: Dale Howard [MVP] on
ks2008 --

When you assign a resource to a task, Microsoft Project 2007 allows you to
enter a Units value for the assignment. The number you enter for the
resource is called the Assignment Units for that resource on the task. Hope
this helps.

--
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


"ks2008" <ks2008(a)discussions.microsoft.com> wrote in message
news:06A7DE18-C119-4B5E-B1D8-20C32EF3A2CE(a)microsoft.com...
> "Fixed Units Indicates that the task's number of assignment units must
> remain constant, regardless of any change in duration or work for the
> task.
> This is the default. For fixed-unit tasks:"
>
> What is "assignment units" means here ?
> Could you please explain ?
>
> Thanks
> KS
>
 | 