From: NotBillable on 12 Jan 2010 10:50 My current Resource Usage view shows my resources and the hours allocated for each resource in hours. How can I change this view so that it tells me the allocated effort for each resource in days, as opposed to hours? thanks in advance.
From: Andrew Lavinsky on 12 Jan 2010 11:13
Tools > Options > Schedule > Work is Entered In.... - Andrew Lavinsky Blog: http://blogs.catapultsystems.com/epm > My current Resource Usage view shows my resources and the hours > allocated for each resource in hours. How can I change this view so > that it tells me the allocated effort for each resource in days, as > opposed to hours? > > thanks in advance. > |