From: NotBillable on
My current Resource Usage view shows my resources and the hours allocated for
each resource in hours. How can I change this view so that it tells me the
allocated effort for each resource in days, as opposed to hours?

thanks in advance.
From: Andrew Lavinsky on
Tools > Options > Schedule > Work is Entered In....


- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm

> My current Resource Usage view shows my resources and the hours
> allocated for each resource in hours. How can I change this view so
> that it tells me the allocated effort for each resource in days, as
> opposed to hours?
>
> thanks in advance.
>