From: Lynn on
I want to draw a horizontal lines on gannt chart which says phase 1
cutoff and phase 2 cut off

how to do this?

Thanks
From: Lynn on
On Oct 31, 6:30 pm, Lynn <moley_c...(a)yahoo.com.au> wrote:
> I want to draw a horizontal lines on gannt chart which says phase 1
> cutoff and phase 2 cut off
>
> how to do this?
>
> Thanks

I meant draw a horizontal line on task entry table
From: G�rard Ducouret on
Lynn,

In the 2007 version, you can set a color and a backgroup pattern for the
selected cells in any table:
Format / font / Backgroup color...

Hope this helps,

G�rard Ducouret

"Lynn" <moley_cruz(a)yahoo.com.au> a �crit dans le message de news:
36c9034c-554a-492f-96f0-9e5f7474552c(a)s21g2000prm.googlegroups.com...
On Oct 31, 6:30 pm, Lynn <moley_c...(a)yahoo.com.au> wrote:
> I want to draw a horizontal lines on gannt chart which says phase 1
> cutoff and phase 2 cut off
>
> how to do this?
>
> Thanks

I meant draw a horizontal line on task entry table



From: Lynn on
i am using project 2003, how can this be done?
From: G�rard Ducouret on
No, in Project 2003 you can only change the color of the font, not the
background.

G�rard Ducouret

"Lynn" <moley_cruz(a)yahoo.com.au> a �crit dans le message de news:
0d85530b-f214-4b39-a07e-54dfa25dac63(a)v37g2000prg.googlegroups.com...
>i am using project 2003, how can this be done?