From: Lynn on 31 Oct 2009 06:30 I want to draw a horizontal lines on gannt chart which says phase 1 cutoff and phase 2 cut off how to do this? Thanks
From: Lynn on 31 Oct 2009 08:55 On Oct 31, 6:30 pm, Lynn <moley_c...(a)yahoo.com.au> wrote: > I want to draw a horizontal lines on gannt chart which says phase 1 > cutoff and phase 2 cut off > > how to do this? > > Thanks I meant draw a horizontal line on task entry table
From: G�rard Ducouret on 31 Oct 2009 09:36 Lynn, In the 2007 version, you can set a color and a backgroup pattern for the selected cells in any table: Format / font / Backgroup color... Hope this helps, G�rard Ducouret "Lynn" <moley_cruz(a)yahoo.com.au> a �crit dans le message de news: 36c9034c-554a-492f-96f0-9e5f7474552c(a)s21g2000prm.googlegroups.com... On Oct 31, 6:30 pm, Lynn <moley_c...(a)yahoo.com.au> wrote: > I want to draw a horizontal lines on gannt chart which says phase 1 > cutoff and phase 2 cut off > > how to do this? > > Thanks I meant draw a horizontal line on task entry table
From: Lynn on 31 Oct 2009 23:42 i am using project 2003, how can this be done?
From: G�rard Ducouret on 1 Nov 2009 04:15 No, in Project 2003 you can only change the color of the font, not the background. G�rard Ducouret "Lynn" <moley_cruz(a)yahoo.com.au> a �crit dans le message de news: 0d85530b-f214-4b39-a07e-54dfa25dac63(a)v37g2000prg.googlegroups.com... >i am using project 2003, how can this be done?
|