From: ellebelle on 20 May 2010 03:08 Hello, I would like to filter for tasks that have work days during a date range in the gant view. eg. I do not want to see a task if it is split during the date range and has no work days assigned. is this possible thanks!
From: Rod Gill on 20 May 2010 07:05 The split one is difficult. You can only determine if a task has work on a particular day in a Usage View. There isn't a filter for work on a particular day, so I suspect you may need a VBA solution. -- Rod Gill Microsoft MVP for Project - http://www.project-systems.co.nz Author of the only book on Project VBA, see: http://www.projectvbabook.com "ellebelle" <ellebelle(a)discussions.microsoft.com> wrote in message news:FA862964-25FD-40C7-9F25-7AE6F58D0B8B(a)microsoft.com... > Hello, > > I would like to filter for tasks that have work days during a date range > in > the gant view. eg. I do not want to see a task if it is split during the > date > range and has no work days assigned. is this possible > > thanks! > > __________ Information from ESET Smart Security, version of virus > signature database 5131 (20100520) __________ > > The message was checked by ESET Smart Security. > > http://www.eset.com > > > __________ Information from ESET Smart Security, version of virus signature database 5131 (20100520) __________ The message was checked by ESET Smart Security. http://www.eset.com
|
Pages: 1 Prev: scaning Next: Projectwise Resource Engaged & Availability report |