From: ellebelle on
I input holidays/sickenss etc into individual resource calendars for each
resource.
When I extend a resourced task into the holiday period of that resource the
Finish date does not calculate the last day worked, but instead the last
duration day.

Is it possible to get this info?

many thanks
From: Jan De Messemaeker on
Hi,

It is in the finish field of the assignment line in Task Usage.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"ellebelle" <ellebelle(a)discussions.microsoft.com> wrote in message
news:E83E48E4-2993-47A0-A050-EA66A8AD4D22(a)microsoft.com...
>I input holidays/sickenss etc into individual resource calendars for each
> resource.
> When I extend a resourced task into the holiday period of that resource
> the
> Finish date does not calculate the last day worked, but instead the last
> duration day.
>
> Is it possible to get this info?
>
> many thanks