From: DJ Huff on 17 May 2010 16:28 I have yet to be able to figure out the formulas that derive both Actual Duration and BCWP when using actual data in my plans. I understand from where the data is to come, but I have not found a consistent set of formulas I can use to calculate Actual Duration, which is essential to calculating % Complete...nor can I figure out how MSP (standalone 2007) calculates BCWP. I have asked the question on this forum in the past as to how MSP calculates the EV elements but have not gotten an answer I can use to run calculations myself and have them = Actual Duration or BCWP I see in the plans. Documentation says Actual Duration / Duration = % Complete (which is what I have set for EV). I cannot figure out Actual Duration. It appears it may use the baseline hours per day within a given period in some fashion, but my calculation results have been inconsistent. I understood BCWP = % Complete * BAC, but that has also been inconsistent. Some documentation implies BCWP uses % Work Complete while others imply % Complete. I need to understand this to be able to make the proper plan adjustments to keep the plans on track. -- Regards, DJ Huff, PhD, PMP, CISA, ITIL
From: "Steve House" sjhouse at hotmail dot on 17 May 2010 17:41
Actual Duration is the amount of calendar time between work began and when it was last performed. Imagine we had a task scheduled to start last Monday and was planned to run for 5 days. The resourced worked as planned Monday and Tuesday then got sick and missed work Wed, Thur and Fri. As of the end of the day Friday, the task had posted 2 days Actual Duration out of 5 days Scheduled duration and is 40% Complete (2/5). The resource returned today and worked all day on it - Actual Duration now is 3 days. The time he was sick becomes non-working time and those days are no longer included in duration. He has come to us this afternoon and said "this is bigger than we thought, it'll take me another 5 days to finish it. Actual Duration (to date) is 3 days, Remaining Duration is 5 days, Total duration is 3+5=8 days and % Complete = 3/8 or 37.5%. Nowhere in these calculations do baselines enter the picture. -- Steve House MS Project Trainer & Consultant "DJ Huff" <DJHuff(a)discussions.microsoft.com> wrote in message news:E3665F4D-8EF9-45C6-9A09-7CB01FC4BA73(a)microsoft.com... >I have yet to be able to figure out the formulas that derive both Actual > Duration and BCWP when using actual data in my plans. I understand from > where the data is to come, but I have not found a consistent set of > formulas > I can use to calculate Actual Duration, which is essential to calculating > % > Complete...nor can I figure out how MSP (standalone 2007) calculates BCWP. > I > have asked the question on this forum in the past as to how MSP calculates > the EV elements but have not gotten an answer I can use to run > calculations > myself and have them = Actual Duration or BCWP I see in the plans. > Documentation says Actual Duration / Duration = % Complete (which is what > I > have set for EV). I cannot figure out Actual Duration. It appears it may > use the baseline hours per day within a given period in some fashion, but > my > calculation results have been inconsistent. I understood BCWP = % > Complete * > BAC, but that has also been inconsistent. Some documentation implies BCWP > uses % Work Complete while others imply % Complete. I need to understand > this to be able to make the proper plan adjustments to keep the plans on > track. > -- > Regards, > > DJ Huff, PhD, PMP, CISA, ITIL |