From: Elvis on
Thanks John.

I only listed the one flag (Variance = "S/" to flag changes in the planned
start), but for each status field I was also collecting and adding this data
to a variable string for each task (i.e. "F/" = finish deltas, "AS/" = actual
start deltas, etc). So I was collecting the data already to have the
ability to filter for the different changes. Don't know why I didn't think
to put the formatting off until the end and format each field as a large
range.

with about 6K lines and many updates you helped me get from about 25-30
minutes to just over 4minutes with this simple change.



"Elvis" wrote:

> Thanks Rod and John
>
> I really need only the changed fields. My "variance" was an idea i had to
> identify changed fields (like your suggestion to flag changed tasks).
> knowing that the there is no direct way to format I will try your suggestion
> John. Thanks
>
>
>
> "John" wrote:
>
> > In article <CED9D422-01F5-49B0-BC91-3AA0C459C300(a)microsoft.com>,
> > Elvis <Elvis(a)discussions.microsoft.com> wrote:
> >
> > > here is what I have now except there are multiple ifs for eacf field
> > > evaluated:
> > >
> > > Sub Status_Evaluation()
> > >
> > > Dim Proj As Project
> > > Dim T As Task
> > >
> > > For Each T In ActiveProject.Tasks
> > >
> > > variance = ""
> > >
> > > If ActiveCell.Task.Start1 <> ActiveCell.Task.Start Then
> > > SelectTaskField Row:=0, Column:="start1"
> > > FontEx Color:=7, CellColor:=5
> > > variance = "S/"
> > > End If
> > >
> > > Application.SelectCellDown
> > >
> > > Next T
> > >
> > > End Sub
> >
> > Elvis,
> > Rod provided a very simple solution that highlights the full task line
> > for the changed rows. Hopefully that gives you something you can use.
> > However if you really want to only highlight those field cells that are
> > changed then the required code is a little more complex.
> >
> > Unfortunately Project does not have the VBA text formatting capabilities
> > found in Excel. Generally text formatting in Project must be done using
> > foreground processing and that takes longer. Your simple macro code is
> > one way to do it but is very slow. There are ways to speed up the
> > process considerably. Here is a pseudo-code structure you might want to
> > pursue.
> > 1. As you enter the change data in the spare fields, also set a flag
> > field
> > 2. Filter on the flag field so the view displays only task rows with
> > changes
> > 3. Select the first row and color format those fields with changes
> > 4. Use Fill Down to color all change task rows
> > 5. Apply the "All Tasks" filter
> >
> > Hope this helps.
> >
> > John
> > Project MVP
> > >
> > >
> > >
> > >
> > >
> > > "Elvis" wrote:
> > >
> > > > I have a decent size schedule that gets statused each week with percent
> > > > work
> > > > complete status, actuals starts, actual finishes and new ECD for start and
> > > > finish. Toss in the fact most items are networked and may need to be
> > > > modified for 'work arounds' this meeting is very time consuming and a large
> > > > portion is spent watching me make the entries.
> > > >
> > > > to cut down on time I have created my own 'que sheet' for holding the
> > > > updates submitted from the team. Instead of having them read off the
> > > > updates
> > > > they've made to a copy of theschedule, they just send it to me. I copy the
> > > > project fields they will be editing and then pasted them into a View
> > > > created
> > > > with Dur1, start1, fin1, start2, fin2, start3, fin3 and a number field to
> > > > hold the percent complete. I then run a macro to compare the deltas from
> > > > their data to what I have in the standard project fields and highlight
> > > > those
> > > > changes. we just walk through and review the changes and afterwards when
> > > > they are all agreed to, I on my one go through and make the changes.
> > > >
> > > > trouble is: I have to access each cell currently in my code to change the
> > > > format and that takes serious time. In excel I can do that WITHOUT
> > > > accessing
> > > > a particular field but do not know how to assign the format in Project.
> > > > any
> > > > help speeding this up is appreciated.
> > > >
> > > > I'll post the code in another string
> > > >
> > > > Thanks so much for any ideas.
> > > >
> > .
> >