From: ProjectRita on 24 May 2010 18:34 hi, I was already seeing some of the answers on this subject, but I am not convinced. It happens that in my project I have 2 types of calendars, one (CALENDAR1) the weekend is considered as non-working days (this include almost every activitie), and in the other saturday is a working day to(CALENDAR2). I can see that is possible to hide the bar tasks on weekends, selecting the non-working time to be in front of tasks bars, but i have tried to change the option for the activities that have the second calendar, but the calendar returns to the base format. Is it possible to do 2 format types, for different calendars? If the answer ir no, is there a way that i can make a collum with the split days for each activities? I ask this, because this will be something that i will have to do every week, but the project that i have to deliver only have 3 weeks, so there only be 3 weekends, and for that the split days will be the same for all activities in calendar 1. I`m allready thinking in another option, if i don`t have a positive return on this questions...maybe the only way, is to do a box, in the weekend bars that only hide the task bars on weekends that belong to calendar1. Thanks for the attention... Regards
From: "Steve House" sjhouse at hotmail dot on 25 May 2010 17:35 You tasks are being scheduled by their respective calendars but the display of the vertical grey bars indicating non-working time is controlled separately by its own calendar. Right click in the timeline, select "timeline" in the pop-up menu and on the non-working page select the calendar you would like to have in control of what days have the grey bar on them. Note that the timeline of the Gantt chart only allows for one calendar to be in cotrol of its formatting, no matter how many different calendars control the various tasks. -- Steve House MS Project Trainer & Consultant "ProjectRita" <ProjectRita(a)discussions.microsoft.com> wrote in message news:0B5FD110-A64E-4BBB-93E2-08913860762A(a)microsoft.com... > hi, > I was already seeing some of the answers on this subject, but I am not > convinced. It happens that in my project I have 2 types of calendars, one > (CALENDAR1) the weekend is considered as non-working days (this include > almost every activitie), and in the other saturday is a working day > to(CALENDAR2). I can see that is possible to hide the bar tasks on > weekends, > selecting the non-working time to be in front of tasks bars, but i have > tried > to change the option for the activities that have the second calendar, but > the calendar returns to the base format. Is it possible to do 2 format > types, > for different calendars? If the answer ir no, is there a way that i can > make > a collum with the split days for each activities? I ask this, because this > will be something that i will have to do every week, but the project that > i > have to deliver only have 3 weeks, so there only be 3 weekends, and for > that > the split days will be the same for all activities in calendar 1. I`m > allready thinking in another option, if i don`t have a positive return on > this questions...maybe the only way, is to do a box, in the weekend bars > that > only hide the task bars on weekends that belong to calendar1. > Thanks for the attention... > Regards
|
Pages: 1 Prev: Need to move a year forward in Gannt Chart Next: Projec 2003: Hyperlinks in HTML Export |