From: LML on 4 Nov 2009 16:49 I'm working with Project 2003 and am finding that work is not summarizing correctly. Here's an example of what I am seeing with 1 resource at 100% Task Name / work / duration 1. User feedback / 20 days / 10 days 1.1. implement feedback on entry / 6 days / 6 days 1.2 implement feedback on approvals / 4 days / 4 days The duration is summarizing correctly, but the work is additional effort and I can't figure out why since the individual tasks are accurate. Any help? Thanks!
|