From: Aimee on 25 Feb 2010 12:26 Thank you, that helps. Aimee "N Birkholz" wrote: > Note that you can MANUALLY set baseline durations by making the Baseline > Duration column visible and then entering valiues. I tend to do that because > my schedule fluctuates a lot in a dynamic environment. > > "Dale Howard [MVP]" wrote: > > > Aimee -- > > > > Keep this principle in mind: "In Microsoft Project, actuals always replace > > estimates." If a task was supposed to take 5 days (a 5-day Duration) and > > the task actually took 8 days (an 8-day Duration), wouldn't you agree that > > the Duration of this task is now 8 days and not the original 5 days? > > > > To capture the original Duration value of each task, you need to save a > > Baseline before you start entering progress in your project. After doing > > this, you can compare the current schedule of the project with the original > > Baseline schedule. To save a Baseline, click Tools - Tracking - Save > > Baseline (Set Baseline in Microsoft Project 2007). Hope this helps. > > > > -- > > Dale A. Howard [MVP] > > VP of Educational Services > > msProjectExperts > > http://www.msprojectexperts.com > > http://www.projectserverexperts.com > > "We write the books on Project Server" > > > > > > "Aimee" <Aimee(a)discussions.microsoft.com> wrote in message > > news:E990EC06-09EE-47A9-8043-CF1F47891635(a)microsoft.com... > > > To capture actual duration I've added the Actual Duration column. If the > > > actual duration is greater than the "planned duration" (i.e. Duration) > > > then > > > MS Project 2007 updates "planned duration" (i.e. Duration) to equal Actual > > > Duration column. This is not what I want. I want Duration to stay the same > > > and Actual to capture the actual time spent on task. > > > > > > Please help. > >
First
|
Prev
|
Pages: 1 2 Prev: HTML Export and Recurring tasks in Project 2003 Next: using session variables in project.aspx |