Prev: ([Finish Variance]/ ProjDateDiff(Phase Start,Phase Finish))
Next: change displayed milestone date?
From: MLS on 4 May 2010 21:51 Hi There - I am trying to add costs to different tasks and for some reason they are not adding up. My column is fixed cost; any suggestions?
From: Andrew Lavinsky on 4 May 2010 22:04 Add the Cost field. That captures both the Fixed and Variable Costs, then rolls them up to the summary level. - Andrew Lavinsky Blog: http://blogs.catapultsystems.com/epm > Hi There - I am trying to add costs to different tasks and for some > reason they are not adding up. My column is fixed cost; any > suggestions? >
From: Trevor Rabey on 4 May 2010 22:23 If you type costs directly into the task Cost field, MSP will interpret this as Fixed Cost, which is any Cost that is associated with a task that does not come from resource costs. You can see this in the Cost Table. Fixed Cost does not roll up. This gives you the possibility of assigning costs to Summaries, which might seem like a good idea but it isn't. For one thing, the macro behind the Analyse Timescaled Data in Excel button on the Analysis Toolbar (MSP2003) extracts task cost but does not extract Summary costs for the Cumulative Cost graph. -- Trevor Rabey 0407213955 61 8 92727485 PERFECT PROJECT PLANNING www.perfectproject.com.au "Andrew Lavinsky" <(Catapult Systems)> wrote in message news:c4abab723258b8ccb9e47b93071b(a)msnews.microsoft.com... > Add the Cost field. That captures both the Fixed and Variable Costs, then > rolls them up to the summary level. > > - Andrew Lavinsky > Blog: http://blogs.catapultsystems.com/epm > >> Hi There - I am trying to add costs to different tasks and for some >> reason they are not adding up. My column is fixed cost; any >> suggestions? >> > >
From: BartH on 6 May 2010 04:02 Today I noticed this same problem - in column Fixed Cost, the values don't add up. I understand the explanation, but can't we do some scripting here to fix this? -- BartH ------------------------------------------------------------------------ BartH's Profile: http://forums.techarena.in/members/217125.htm View this thread: http://forums.techarena.in/microsoft-project/1333533.htm http://forums.techarena.in
From: Andrew Lavinsky on 6 May 2010 08:52 But there's no problem. Fixed Costs are entered in the Fixed Cost field. Variable Costs are entered in the Resource Sheet. Cost sums them all up. If you'd like to sum up Fixed Cost on it's own, just create a new custom field and set it to equal "Fixed Cost." Then make sure it's rolling up the sum to the Summary level. - Andrew Lavinsky Blog: http://blogs.catapultsystems.com/epm > Today I noticed this same problem - in column Fixed Cost, the values > don't add up. > I understand the explanation, but can't we do some scripting here to > fix > this? > http://forums.techarena.in >
|
Next
|
Last
Pages: 1 2 3 Prev: ([Finish Variance]/ ProjDateDiff(Phase Start,Phase Finish)) Next: change displayed milestone date? |