From: Gary D on
I have a 20 day task called shutter, steel and concrete on a programme. I am
assigning labour resource across the whole activity, however every 4th day i
will be concreting, therefore i want to assign a concrete pump every 4th day
on this single activity. I do not want to create 5 seperate concreting
tasks. Is this possible on Microsoft Project?
-
GDD
From: Trevor Rabey on
I recognise this typical construction project scenario.
I will say what has already been said in several other similar recent posts
on this subject.
Why the reluctance to simply sub-divide or decompose the tasks into more
tasks, with simple FS0 predecessor links, when this is the obvious solution?
More tasks = more simple = more control.
Problem solved, plan finished.
Readable, trackable, updatable, controllable.
Your 20 day task, which merges three obviously separate tasks, is just too
long and not well enough defined.
Below this level of sub-division, you have no visibility and no control.

I can advise various ways to make your bars look like they are in the right
place, such as FS+4 and FS+8 predecessor links, but I cannot advise a better
method than just making more tasks.
--
Trevor Rabey
0407213955
61 8 92727485
PERFECT PROJECT PLANNING
www.perfectproject.com.au

"Gary D" <GaryD(a)discussions.microsoft.com> wrote in message
news:0F77C7B9-ECB3-4232-AB36-DFA85CCDB106(a)microsoft.com...
>I have a 20 day task called shutter, steel and concrete on a programme. I
>am
> assigning labour resource across the whole activity, however every 4th day
> i
> will be concreting, therefore i want to assign a concrete pump every 4th
> day
> on this single activity. I do not want to create 5 seperate concreting
> tasks. Is this possible on Microsoft Project?
> -
> GDD


From: Trevor Rabey on
See this thread:

SS + so and so days predecessor logic

on 1/12/2009
--
Trevor Rabey
0407213955
61 8 92727485
PERFECT PROJECT PLANNING
www.perfectproject.com.au

"Gary D" <GaryD(a)discussions.microsoft.com> wrote in message
news:0F77C7B9-ECB3-4232-AB36-DFA85CCDB106(a)microsoft.com...
>I have a 20 day task called shutter, steel and concrete on a programme. I
>am
> assigning labour resource across the whole activity, however every 4th day
> i
> will be concreting, therefore i want to assign a concrete pump every 4th
> day
> on this single activity. I do not want to create 5 seperate concreting
> tasks. Is this possible on Microsoft Project?
> -
> GDD


From: Jim Aksel on
Assign "Concrete Pump" to the task. Then View/Task Usage on the menu. You
can adjust the assignment units from the right side of the task Usage view.

Good scheduling practices would break this task down into smaller pieces
with many subtasks.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com



"Gary D" wrote:

> I have a 20 day task called shutter, steel and concrete on a programme. I am
> assigning labour resource across the whole activity, however every 4th day i
> will be concreting, therefore i want to assign a concrete pump every 4th day
> on this single activity. I do not want to create 5 seperate concreting
> tasks. Is this possible on Microsoft Project?
> -
> GDD
 | 