From: ks2008 on 9 Dec 2009 09:05 Hi All, I could able to create the "Cross project Link", but how do I view the link details, just I created ? Thanks KS -- ks2008 ------------------------------------------------------------------------ ks2008's Profile: http://forums.techarena.in/members/106957.htm View this thread: http://forums.techarena.in/microsoft-project/1280321.htm http://forums.techarena.in
From: JulieS on 9 Dec 2009 09:26 Hello ks2008, The external predecessor/successor information should show in the predecessor field. Double click on the external task and it will open the project containing the cross-project link. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "ks2008" <ks2008.42xkvc(a)DoNotSpam.com> wrote in message news:ks2008.42xkvc(a)DoNotSpam.com... > > Hi All, > I could able to create the "Cross project Link", but how do I view > the > link details, just I created ? > Thanks > KS > > > -- > ks2008 > ------------------------------------------------------------------------ > ks2008's Profile: http://forums.techarena.in/members/106957.htm > View this thread: > http://forums.techarena.in/microsoft-project/1280321.htm > > http://forums.techarena.in >
From: ks2008 on 9 Dec 2009 23:57 Yes, if I click on the external task in proj01, it open the project( proj02) containing the cross-project link. However Predecessors & Successors` fields are empty ( see, proj 01). Still I am not clear. How I could view the link for the extranal task I created in proj01 ? How I could say the task is an extranal task with out clicking on it ? and the link of that an external task.? Note: Proj01 is the project conaining external task. Task # 13, 14 & 15 are external task in Proj01. Proj01 ===== ID Project Task name Priority Predecessors Successors` Start 12 Tea01 Creamer 500 Wed 12/2/09 13 Tea01 get Sugar03 500 Tue 11/17/09 14 Tea01 Get Water03 500 Tue 11/17/09 15 Tea01 Get leaves03 500 Tue 11/17/09 Proj02 ===== 13 Tea01 get Sugar03 500 Tue 11/17/09 14 Tea01 Get Water03 500 Tue 11/17/09 15 Tea01 Get leaves03 500 Tue 11/17/09 Thanks KS -- ks2008 ------------------------------------------------------------------------ ks2008's Profile: http://forums.techarena.in/members/106957.htm View this thread: http://forums.techarena.in/microsoft-project/1280321.htm http://forums.techarena.in
From: JulieS on 10 Dec 2009 09:58 Hi ks2008, I think we may be talking about two different things. There is a difference between external predecessors/successors and "links" which show up under the Edit > Links command. The Edit > Links shows information linked through OLE (Object Linking and embedding) and is created through a copy/paste special, link command. If you've created the "link" through copy/paste special, there will not be anything showing in the predecessor/successor field. However, those types of links are *not* external predecessors and successors. External predecessors/successors can be created by making a consolidated project, selecting the two tasks and clicking the Link Tasks button. My guess is that you did not create external predecessors and successors. If you have the option "Show external predecessors and successors selected" on the View tab of the Options dialog box, you should see both the external task in the Task table as well as the gray task bar showing in the Gantt chart. You should also see the information in the predecessor or successors field. See Help on creating links between tasks in different projects. From your description, it appears as though you may have created "links" through a copy/paste link command and not through the creation of external predecessors and successors. I hope this helps. Julie "ks2008" <ks2008.42yqjb(a)DoNotSpam.com> wrote in message news:ks2008.42yqjb(a)DoNotSpam.com... > > Yes, if I click on the external task in proj01, it open the > project( > proj02) containing the cross-project link. > However Predecessors & Successors` fields are empty ( see, proj > 01). > > Still I am not clear. > How I could view the link for the extranal task I created in > proj01 ? > How I could say the task is an extranal task with out clicking on > it ? > and the link of that an external task.? > > Note: Proj01 is the project conaining external task. > Task # 13, 14 & 15 are external task in Proj01. > > > Proj01 > ===== > ID Project Task name Priority Predecessors Successors` Start > 12 Tea01 Creamer 500 Wed 12/2/09 > 13 Tea01 get Sugar03 500 Tue 11/17/09 > 14 Tea01 Get Water03 500 Tue 11/17/09 > 15 Tea01 Get leaves03 500 Tue 11/17/09 > > > > > Proj02 > ===== > 13 Tea01 get Sugar03 500 Tue 11/17/09 > 14 Tea01 Get Water03 500 Tue 11/17/09 > 15 Tea01 Get leaves03 500 Tue 11/17/09 > > Thanks > KS > > > -- > ks2008 > ------------------------------------------------------------------------ > ks2008's Profile: http://forums.techarena.in/members/106957.htm > View this thread: > http://forums.techarena.in/microsoft-project/1280321.htm > > http://forums.techarena.in >
From: ks2008 on 10 Dec 2009 16:44 You are perfect. Thanks for your detailed explanation. Thanks KS -- ks2008 ------------------------------------------------------------------------ ks2008's Profile: http://forums.techarena.in/members/106957.htm View this thread: http://forums.techarena.in/microsoft-project/1280321.htm http://forums.techarena.in
|