From: Satya on 21 Apr 2010 05:48 Hi, We have two tasks with task1 has *SF* dependency on task2 as follows Task Id | Task Name | Duration |Start |Finish| Dependency | Resource Names 1 | Task1 | 1 day | April 20, 2010 8:00 AM | April 21, 2010 9:00 AM | 2SF | R1 2 | Task2 | 2 days | April 21, 2010 9:00 AM | April 23, 2010 9:00 PM| |R2 R1 is on vacation on 21st April MPP displays the end of Task1 as April 21, 2010 9:00 PM Issue: As R1 is on vacation on 21st, expectation is that the Task1 should finish on 20th Apr not on 21st Apr. How can we resolve this issue in MS Project 2007? Regards Satya
From: Jan De Messemaeker on 21 Apr 2010 06:42 Hi, Your dependency tells task 1 not to finish before Task 2 starts. That's what Project does for you. The task can by no means end on April 20 because of this dependency. -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Satya" <Satya(a)discussions.microsoft.com> wrote in message news:86B4FF88-627B-4D57-980F-35DE42264857(a)microsoft.com... > Hi, > We have two tasks with task1 has *SF* dependency on task2 as follows > Task Id | Task Name | Duration |Start |Finish| Dependency | Resource Names > 1 | Task1 | 1 day | April 20, 2010 8:00 AM | > April > 21, 2010 9:00 AM | 2SF | R1 > 2 | Task2 | 2 days | April 21, 2010 9:00 AM | > April > 23, 2010 9:00 PM| |R2 > R1 is on vacation on 21st April > MPP displays the end of Task1 as April 21, 2010 9:00 PM > Issue: As R1 is on vacation on 21st, expectation is that the Task1 should > finish on 20th Apr not on 21st Apr. > How can we resolve this issue in MS Project 2007? > Regards > Satya
|
Pages: 1 Prev: Project 2010 Next: Partial predecessor |