From: Jpstewar on
Scenario: Information from task A is needed for task B, which is a meeting
(or milestone) on the project plan - think of it as task 3, the MRC
pre-meeting. Task A does NOT have to be finished by the time of the meeting,
but some information is needed. We are calling A a predecessor to B, but
maybe that is not correct. We just need information from A so let's say A
needs to be 25% complete. Is there a way of capturing that?
From: Dale Howard [MVP] on
Jpstewar --

Link task A and task B with the default Finish-to-Start dependency. In the
Gantt Chart, double-click the link line between task A and task B (it's the
easiest to double-click on the arrow head at the end of the link line). In
the Task Dependency dialog, select the Start-to-Start dependency and then
enter 25% in the Lag field. Alternately, leave the Finish-to-Start
dependency selected and enter -75% in the Lag field. In either situation,
click the OK button and you have modeled the dependency relationship you
seek. Hope this helps.

--
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


"Jpstewar" <Jpstewar(a)discussions.microsoft.com> wrote in message
news:DC0EC490-9E83-494B-8552-0379104279FD(a)microsoft.com...
> Scenario: Information from task A is needed for task B, which is a meeting
> (or milestone) on the project plan - think of it as task 3, the MRC
> pre-meeting. Task A does NOT have to be finished by the time of the
> meeting,
> but some information is needed. We are calling A a predecessor to B, but
> maybe that is not correct. We just need information from A so let's say A
> needs to be 25% complete. Is there a way of capturing that?

From: Trevor Rabey on
Alternatively, confine yourself to simple FS links with no lag (because life
is easier that way) by splitting Task A into A1 and A2, then FS0 from A1 to
A2 and FS0 from A1 to B.
--
Trevor Rabey
0407213955
61 8 92727485
PERFECT PROJECT PLANNING
www.perfectproject.com.au

"Jpstewar" <Jpstewar(a)discussions.microsoft.com> wrote in message
news:DC0EC490-9E83-494B-8552-0379104279FD(a)microsoft.com...
> Scenario: Information from task A is needed for task B, which is a meeting
> (or milestone) on the project plan - think of it as task 3, the MRC
> pre-meeting. Task A does NOT have to be finished by the time of the
> meeting,
> but some information is needed. We are calling A a predecessor to B, but
> maybe that is not correct. We just need information from A so let's say A
> needs to be 25% complete. Is there a way of capturing that?


From: Jpstewar on
I tried these and it looks like they both have the same end result. B starts
25% of the way into A. So it seems moot as to whether you use F to S or S to
S. Either way, same end result, yes?

"Dale Howard [MVP]" wrote:

> Jpstewar --
>
> Link task A and task B with the default Finish-to-Start dependency. In the
> Gantt Chart, double-click the link line between task A and task B (it's the
> easiest to double-click on the arrow head at the end of the link line). In
> the Task Dependency dialog, select the Start-to-Start dependency and then
> enter 25% in the Lag field. Alternately, leave the Finish-to-Start
> dependency selected and enter -75% in the Lag field. In either situation,
> click the OK button and you have modeled the dependency relationship you
> seek. Hope this helps.
>
> --
> Dale A. Howard [MVP]
> VP of Educational Services
> msProjectExperts
> http://www.msprojectexperts.com
> http://www.projectserverexperts.com
> "We write the books on Project Server"
>
>
> "Jpstewar" <Jpstewar(a)discussions.microsoft.com> wrote in message
> news:DC0EC490-9E83-494B-8552-0379104279FD(a)microsoft.com...
> > Scenario: Information from task A is needed for task B, which is a meeting
> > (or milestone) on the project plan - think of it as task 3, the MRC
> > pre-meeting. Task A does NOT have to be finished by the time of the
> > meeting,
> > but some information is needed. We are calling A a predecessor to B, but
> > maybe that is not correct. We just need information from A so let's say A
> > needs to be 25% complete. Is there a way of capturing that?
>
From: Dale Howard [MVP] on
Jpstewar --

Yup, both end up with pretty much the same result. I personally like the
first approach. I know that others like the latter approach. Choose one
and go for it! :) Hope this helps.

--
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


"Jpstewar" <Jpstewar(a)discussions.microsoft.com> wrote in message
news:EC87B576-556F-4213-8EF4-73D1A4476CF0(a)microsoft.com...
> I tried these and it looks like they both have the same end result. B
> starts
> 25% of the way into A. So it seems moot as to whether you use F to S or S
> to
> S. Either way, same end result, yes?
>
> "Dale Howard [MVP]" wrote:
>
>> Jpstewar --
>>
>> Link task A and task B with the default Finish-to-Start dependency. In
>> the
>> Gantt Chart, double-click the link line between task A and task B (it's
>> the
>> easiest to double-click on the arrow head at the end of the link line).
>> In
>> the Task Dependency dialog, select the Start-to-Start dependency and then
>> enter 25% in the Lag field. Alternately, leave the Finish-to-Start
>> dependency selected and enter -75% in the Lag field. In either
>> situation,
>> click the OK button and you have modeled the dependency relationship you
>> seek. Hope this helps.
>>
>> --
>> Dale A. Howard [MVP]
>> VP of Educational Services
>> msProjectExperts
>> http://www.msprojectexperts.com
>> http://www.projectserverexperts.com
>> "We write the books on Project Server"
>>
>>
>> "Jpstewar" <Jpstewar(a)discussions.microsoft.com> wrote in message
>> news:DC0EC490-9E83-494B-8552-0379104279FD(a)microsoft.com...
>> > Scenario: Information from task A is needed for task B, which is a
>> > meeting
>> > (or milestone) on the project plan - think of it as task 3, the MRC
>> > pre-meeting. Task A does NOT have to be finished by the time of the
>> > meeting,
>> > but some information is needed. We are calling A a predecessor to B,
>> > but
>> > maybe that is not correct. We just need information from A so let's
>> > say A
>> > needs to be 25% complete. Is there a way of capturing that?
>>