From: Chris_J_S on 21 May 2010 16:29 okay, I'm going nuts with this one. BCWP is always equal to ACWP. Everytime I enter the %complete, it loads the actual work values into the resource usage table. Actual work comes to me from the CAM, which is off the labor reports. I need to load this into the actual work field, on a per week basis. When I do that, the work field gets updated and BCWP still equals ACWP. How do I tell this thing to stop spreading the work?
From: JulieS on 21 May 2010 16:53 Hi Chris_J_S, Have you tried entering the Actual Work into either the Task Usage or Resource usage view? The right hand side can be configured to show Actual Work -- you can have much greater control over where the work gets spread. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 5/21/2010 4:29 PM, Chris_J_S wrote: > okay, I'm going nuts with this one. BCWP is always equal to ACWP. Everytime > I enter the %complete, it loads the actual work values into the resource > usage table. Actual work comes to me from the CAM, which is off the labor > reports. I need to load this into the actual work field, on a per week > basis. When I do that, the work field gets updated and BCWP still equals > ACWP. How do I tell this thing to stop spreading the work?
From: Andrew Lavinsky on 24 May 2010 09:03 In addition to Julie's suggestion, it seems kind of weird to me that you're using % Complete to update tasks with Earned Value. Can't say I've seen much of that, as usually people end up using some measure of Actuals Work as she suggested. If you do wish to use % Complete, you may wish to look at the options in Tools > Options > Calculation. You'll see a number of items that control how % Complete is applied to a task relative to the Status Date. That may also help with your issue. - Andrew Lavinsky Blog: http://blogs.catapultsystems.com/epm > Hi Chris_J_S, > > Have you tried entering the Actual Work into either the Task Usage or > Resource usage view? The right hand side can be configured to show > Actual Work -- you can have much greater control over where the work > gets spread. > > I hope this helps. Let us know how you get along. > > Julie > Project MVP > Visit http://project.mvps.org/ for the FAQs and additional information > about Microsoft Project > > On 5/21/2010 4:29 PM, Chris_J_S wrote: > >> okay, I'm going nuts with this one. BCWP is always equal to ACWP. >> Everytime I enter the %complete, it loads the actual work values into >> the resource usage table. Actual work comes to me from the CAM, >> which is off the labor reports. I need to load this into the actual >> work field, on a per week basis. When I do that, the work field gets >> updated and BCWP still equals ACWP. How do I tell this thing to stop >> spreading the work? >>
|
Pages: 1 Prev: Highlight Individual Rows Next: Highlight Task in Red |