From: William on 26 Nov 2009 16:44 I'm planning and managing a project's schedule through a unique optimization process that joins the task-dependent critical path with the critical chain, CCPM "Critical Chain Project Manager". Do you have some solution to add buffers and manage whit this methodology the projects?
From: vanita on 26 Nov 2009 22:52 Hi William You may use the software 'Concerto'. That is best suited for CCPM. In MSP if we want to practice CCPM, we may add a task as buffer at the end of Critical chain and Feeder chains, instead of adding buffer component in each activity duration. I hope it helps. Vanita -- Project Management consultant and trainer vanita_ahuja(a)yahoo.com "William" wrote: > I'm planning and managing a project's schedule through a unique optimization > process that joins the task-dependent critical path with the critical chain, > CCPM "Critical Chain Project Manager". Do you have some solution to add > buffers and manage whit this methodology the projects?
|
Pages: 1 Prev: Task Duration vs Actual Effort vs Actual start date Next: Could Windows be like this : |