From: Sumit on 26 Nov 2009 06:42 Hi... I have tasks with task type as fixed duration. While importing data for assignments for that task I notice that the DURATION gets AUTOMATICALLY changed in 2 cases:- 1) When I am importing actual effort for assignment or 2) When I import actual start date for that assignment( assignment doesn't have actual finish date as of now). I am not able to find the logic why MSP is doing that. Any help or insight into the behavior is really appreciated!! Thanks a lot in advance!!! -- --Sumit
From: Jan De Messemaeker on 26 Nov 2009 07:11 Hi, I gave up wondering WHY the makers of Project have selected some seemingly unlogical options like this one. I'm afraid we can't change it. -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Sumit" <Sumit(a)discussions.microsoft.com> wrote in message news:9A1D32A1-654C-4960-8A23-162E5CDE2271(a)microsoft.com... > Hi... > > I have tasks with task type as fixed duration. > > While importing data for assignments for that task I notice that the > DURATION gets AUTOMATICALLY changed in 2 cases:- > > 1) When I am importing actual effort for assignment > or > 2) When I import actual start date for that assignment( assignment doesn't > have actual finish date as of now). > > I am not able to find the logic why MSP is doing that. > > Any help or insight into the behavior is really appreciated!! > > Thanks a lot in advance!!! > > -- > --Sumit
|
Pages: 1 Prev: Urgent : Duration getting automatically changed Next: CCPM |