From: MarkP on 26 Jan 2010 11:08 Jan, Soooo sorry for the late response. This is exactly what I needed. THANKS ! MarkP "Jan De Messemaeker" wrote: > Hi, > > Calendar View > Format Menu > Bar Styles > Select All > In text, replace Name by Resource Names > > HTH > > -- > Jan De Messemaeker > Microsoft Project Most Valuable Professional > +32 495 300 620 > For availability check: > http://users.online.be/prom-ade/Calendar.pdf > "MarkP" <MarkP(a)discussions.microsoft.com> wrote in message > news:8D2DBC37-7FDD-4E0D-BBD7-7811B9D37B9B(a)microsoft.com... > > Using MS Project 2007, I have created an Administrative project plan to > > account for all time off. > > > > I would like to have the admin staff print the time off calendar for easy > > viewing. > > > > Unfortunately, the task name display and not the resource name. > > > > Is it possible to display the resource name instead ? > > - MarkP > > > . >
|
Pages: 1 Prev: Maintain tasks close to each other Next: Can I link my Project with my Blackberry? |