From: Franco Lombardo on 26 Jan 2010 06:40 I have 2 tasks that must be done in sequence and in a consecutive way. How can I force Project to keep them close to each other during the resource level phase? Thanks. Bye Franco ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ http://www.francolombardo.net Scala, Java, As400..... http://twitter.com/f_lombardo ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
From: Sai on 26 Jan 2010 07:18 Franco Lombardo wrote: > I have 2 tasks that must be done in sequence and in a consecutive way. How > can I force Project to keep them close to each other during the resource > level phase? > > Thanks. > > Bye > > Franco > > ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ > http://www.francolombardo.net > Scala, Java, As400..... > http://twitter.com/f_lombardo > ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ If you want the tasks to be sequencial, then have FS dependency btwn them. Just wondering why you looking at resource levelling. Do you have same resource on both the tasks? If yes, you need to use the settings of Resource Levelling and adjust the delay *manually* Pl let us know if this helps Sai, PMP PMI-SP MCT MCTS http://saipower.wordpress.com
From: Franco Lombardo on 26 Jan 2010 08:49 > If you want the tasks to be sequencial, then have FS dependency btwn > them. I did it. > Just wondering why you looking at resource levelling. Do you have same > resource on both the tasks? Yes. > If yes, you need to use the settings of > Resource Levelling and adjust the delay *manually* Oh :-( Thanks Bye Franco
From: Sai on 26 Jan 2010 10:26 On Jan 26, 6:49 pm, "Franco Lombardo" <f_lomba...(a)hotmail.com> wrote: > > If you want the tasks to be sequencial, then have FS dependency btwn > > them. > > I did it. > > > Just wondering why you looking at resource levelling. Do you have same > > resource on both the tasks? > > Yes. > > > If yes, you need to use the settings of > > Resource Levelling and adjust the delay *manually* > > Oh :-( > > Thanks > > Bye > > Franco Franco - Let me try to make you :-) to some extent. If you want the leveling (delay) to be applied automatically, set the "Leveling calculations" to Automatic in "Resource Leveling" dialog box. Few points to remember: 1. The above said setting, will auto delay the tasks on all resources who are overallocated 2. You need to optimize the settings under "Resource Overallocations" section in "Resource Leveling" dialog box to get the best fit; but cant promise Please let us know if this helps Sai, PMP PMI-SP MCT MCTS http://saipower.wordpress.com
From: Franco Lombardo on 27 Jan 2010 08:05 "Mike Glen" wrote > Welcome to this Microsoft Project newsgroup :) Thank you very much! :-) > Give the two tasks a high priority, say 900, and then use levelling. I tried, but it didn't work. :-( I partially solved this way: after project levelling, I went to each of the starting tasks and I set "Constraint type" to "Finish no earlier than". Note that I didn't set any constranint date, but that Project 2010 automatically sets a constraint date in a way I don't understand. After this "magic", the dates are now close each other. I'd like to realize if this fits only for my particular project, that, by the way, is programmed "as late as possible", or if it's a standard behavior. Thanks to all for the kind answers. Bye Franco ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ http://www.francolombardo.net Scala, Java, As400..... http://twitter.com/f_lombardo ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
|
Next
|
Last
Pages: 1 2 Prev: Resource usage view as a Web report Next: Calendar View - Display Resource Name |