From: Jason on
How can you get sub totals for summary task in your cashflow reports?
From: JulieS on
Hello Jason,

Unfortunately while the Summary tasks do show in the default Cash flow
report, the values from the tasks (where money is actually applied
through the assignment of resources) do not "roll - up" to the summary
tasks.

You will likely have better luck printing the Task Usage view after
adding Cost to the right (timescaled) portion of the view.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 2/1/2010 4:18 PM, Jason wrote:
> How can you get sub totals for summary task in your cashflow reports?