From: vro on 1 Feb 2010 15:03 What's the easiest way to get the total hours, broken down by resource for a particular summary task?
From: Jan De Messemaeker on 1 Feb 2010 15:17 Hi, Resourced Usage View Project menu Group By, New Group Click Group assignments, not resources Group by Task Outline number (assignments) Then By Name (resource) That's it. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availabliy check: http://users.online.be/prom-ade/Calendar.pdf "vro" <vro(a)discussions.microsoft.com> wrote in message news:382DEB9F-2799-4D0C-84DF-BF4891D75431(a)microsoft.com... > What's the easiest way to get the total hours, broken down by resource for > a > particular summary task?
From: vro on 2 Feb 2010 00:22 that worked like a charm! Thanks! --- frmsrcurl: http://msgroups.net/microsoft.public.project/how-to-display-work-by-resource-for-a-summary-task
From: Jan De Messemaeker on 2 Feb 2010 02:44 You're welcome! -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availabliy check: http://users.online.be/prom-ade/Calendar.pdf "vro" <user(a)msgroups.net/> wrote in message news:OAlmEf8oKHA.5508(a)TK2MSFTNGP02.phx.gbl... > that worked like a charm! Thanks! > > --- > frmsrcurl: > http://msgroups.net/microsoft.public.project/how-to-display-work-by-resource-for-a-summary-task
|
Pages: 1 Prev: changing settings to non-standard work week Next: Cashflow Summary Task |