From: Jim Patterson on 5 May 2010 16:22 In Project 2007, I am completing a task. After briefly displaying the green completion checkmark, the checkmark disappears. The task is not a summary task. Any suggestions are appreciated. -- Jim Patterson
From: JulieS on 5 May 2010 18:10
Are you seeing the checkmark in the Indicator column or is this showing in a custom field? I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 5/5/2010 4:22 PM, Jim Patterson wrote: > In Project 2007, I am completing a task. After briefly displaying the green > completion checkmark, the checkmark disappears. The task is not a summary > task. > > Any suggestions are appreciated. |