From: TMI Contractors on 5 May 2010 16:02 Is there anyway to tie several activities together so that they happen on the same date?? -- TMI Contractors ------------------------------------------------------------------------ TMI Contractors's Profile: http://forums.techarena.in/members/216904.htm View this thread: http://forums.techarena.in/microsoft-project/1334224.htm http://forums.techarena.in
From: Rod Gill on 5 May 2010 17:03 Hi, You should link them all to the Task that triggers them all to start. -- Rod Gill Microsoft MVP for Project - http://www.project-systems.co.nz Author of the only book on Project VBA, see: http://www.projectvbabook.com "TMI Contractors" <TMI.Contractors.4aiaxc(a)DoNotSpam.com> wrote in message news:TMI.Contractors.4aiaxc(a)DoNotSpam.com... > > Is there anyway to tie several activities together so that they happen > on the same date?? > > > -- > TMI Contractors > ------------------------------------------------------------------------ > TMI Contractors's Profile: http://forums.techarena.in/members/216904.htm > View this thread: http://forums.techarena.in/microsoft-project/1334224.htm > > http://forums.techarena.in > > > __________ Information from ESET Smart Security, version of virus > signature database 5089 (20100505) __________ > > The message was checked by ESET Smart Security. > > http://www.eset.com > > > __________ Information from ESET Smart Security, version of virus signature database 5089 (20100505) __________ The message was checked by ESET Smart Security. http://www.eset.com
From: Jim Aksel on 5 May 2010 17:40 Link the tasks using a "Start to Start" relationship. For example, highlight Task A and Task B. Select the chain link icon (this establishes a Finish To Start relationship). Double click Task B. Pull the Predecessors tab. Change the type from FS to SS -- If this post was helpful, please consider rating it. Jim Aksel, MVP Check out my blog for more information: http://www.msprojectblog.com "TMI Contractors" wrote: > > Is there anyway to tie several activities together so that they happen > on the same date?? > > > -- > TMI Contractors > ------------------------------------------------------------------------ > TMI Contractors's Profile: http://forums.techarena.in/members/216904.htm > View this thread: http://forums.techarena.in/microsoft-project/1334224.htm > > http://forums.techarena.in > > . >
From: Deepak_Malhotra on 7 May 2010 07:52 yes, just make the duration to 0 days.... this will work even if the dependency of the task if there... say there are 10 tasks related to each other which means that 2nd task start only when first task is finished...so if just make the duration as 0 for all, the task date become common for all the related tasks... hope this helps.. :) -- Deepak_Malhotra ------------------------------------------------------------------------ Deepak_Malhotra's Profile: http://forums.techarena.in/members/217556.htm View this thread: http://forums.techarena.in/microsoft-project/1334224.htm http://forums.techarena.in
|
Pages: 1 Prev: Completion Checkmark Next: Microsoft Software used in Alternative Fuel Source |