From: Redrover on
I finally did an export of the project to excel and imported it into a new
project file and the bars are all showing up. Thanks for the suggestions!!

"Andrew Lavinsky" wrote:

> One more obvious though, are you sure you're not setting a SNET constraint
> from last year that is pushing the bars off the currently visible date range
> in the Gantt Chart?
>
>
> - Andrew Lavinsky
> Blog: http://blogs.catapultsystems.com/epm
>
> > Any flag fields configured with a formula depending on the constraint
> > type?
> > Any filters applied? Unidentified macros lurking in the background?
> > - Andrew Lavinsky
> > Blog: http://blogs.catapultsystems.com/epm
> >> I'm looking at a project someone else created and trying to figure
> >> out why the gantt bars disappear from view when I set a 'start no
> >> earlier than' constraint. I've checked for hidden bars, looked at the
> >> formatting options, etc. Any suggestions on what to look at next.
> >>
>
>
> .
>