From: Sai on 26 Jan 2010 10:12 On Jan 26, 7:04 pm, Christian W <Christi...(a)discussions.microsoft.com> wrote: > :)) thanks by the reponses.. I have a example for duracion fixed and work fixed > > My task may be 40 days of duration AND 40 hours of work, then I need that > project calculate resource units, filling 40 hours in this 40 day if have > disponibility. > > I think that SAI response is a good alternative.. > > Thanks in advance and I'll move to los angeles > Christian Thanks Christian for confirming the solution works! Have a great day ahead ...