From: Sai on
On Jan 26, 7:04 pm, Christian W <Christi...(a)discussions.microsoft.com>
wrote:
> :)) thanks by the reponses.. I have a example for duracion fixed and work fixed
>
> My task may be 40 days of duration AND 40 hours of work, then I need that
> project calculate resource units, filling 40 hours in this 40 day if have
> disponibility.
>
> I think that SAI response is a good alternative..
>
> Thanks in advance and I'll move to los angeles
> Christian

Thanks Christian for confirming the solution works! Have a great day
ahead ...