From: Christian W on 25 Jan 2010 14:37 Hello, I need to do one taks with "duration fixed AND Work Fied" is this possible ? I need that dont move duration and work but units be variable.. I cant. Sorry my english and thanks in advance, Christian W
From: Dale Howard [MVP] on 25 Jan 2010 20:23 Christian W -- No, you CANNOT fix both Duration and Work. Sorry. -- Dale A. Howard [MVP] VP of Educational Services msProjectExperts http://www.msprojectexperts.com http://www.projectserverexperts.com "We write the books on Project Server" "Christian W" <ChristianW(a)discussions.microsoft.com> wrote in message news:C033B583-E52A-4F58-93F6-96BA62C4AC72(a)microsoft.com... > Hello, > > I need to do one taks with "duration fixed AND Work Fied" is this possible > ? > > I need that dont move duration and work but units be variable.. > > > I cant. > > Sorry my english and thanks in advance, > Christian W
From: Jim Aksel on 25 Jan 2010 20:34 Might you try making a task Fixed Duration and then key the value of Work in the Work column. This will adjust the resource assignment units. Christian, your English is fine ... better than some here in Los Angeles. -- If this post was helpful, please consider rating it. Jim Aksel, MVP Check out my blog for more information: http://www.msprojectblog.com "Christian W" wrote: > Hello, > > I need to do one taks with "duration fixed AND Work Fied" is this possible ? > > I need that dont move duration and work but units be variable.. > > > I cant. > > Sorry my english and thanks in advance, > Christian W
From: Sai on 26 Jan 2010 03:59 On Jan 26, 12:37 am, Christian W <Christi...(a)discussions.microsoft.com> wrote: > Hello, > > I need to do one taks with "duration fixed AND Work Fied" is this possible ? > > I need that dont move duration and work but units be variable.. > > I cant. > > Sorry my english and thanks in advance, > Christian W Yes, you can -- to some extent. Have the task type as "Fixed Duration" and have "Effort driven" as yes. What does this mean? - Let's say you have entered the duration (5 days) and work (40 hr) of a task, and have applied the above said settings. During the initial resource assignment, project calculates the units of the resources -- John[100%]. If you alter the assignment units of the resource on that task -- John[50%], the "work" column will change -- 20hrs -- as task type is fixed duration, and so the work should naturally change. Please let us know if this helps -Sai, PMP, PMI-SP, MCT, MCTS http://saipower.wordpress.com
From: Christian W on 26 Jan 2010 09:04 :)) thanks by the reponses.. I have a example for duracion fixed and work fixed My task may be 40 days of duration AND 40 hours of work, then I need that project calculate resource units, filling 40 hours in this 40 day if have disponibility. I think that SAI response is a good alternative.. Thanks in advance and I'll move to los angeles Christian
|