From: Redrover on 12 May 2010 15:02 I'm looking at a project 2007 file that has constraints applied to many of the tasks. The gantt bars do not show. If I remove the constraint the gantt bars appear. Any ideas on what's happening?
From: John on 12 May 2010 15:56 In article <D58974E8-84BB-4D18-9507-7CDEE5C80778(a)microsoft.com>, Redrover <Redrover(a)discussions.microsoft.com> wrote: > I'm looking at a project 2007 file that has constraints applied to many of > the tasks. The gantt bars do not show. If I remove the constraint the gantt > bars appear. Any ideas on what's happening? Redrover, My first guess is that the constraint is pushing the task out of the view range (i.e. earlier or later than currently shows on the Gantt Chart display). Try selecting on of the "invisible" tasks and then use the Go To Task icon on the toolbar. Hope this helps. John Project MVP
|