From: karens on
I have a master project with approximately 30 subprojects. Each project has
a project manager. I want to be able to run a report that shows the project
managers and the activities that fall under that project manager within a
certain timeframe. Ultimately, I'd also like to be able to have a graph or
chart that shows how much % of work the PM has during a time frame. I'm
fairly new to Project, used to use Primavera. Can anyone help??
My report would look something like this:

Week 1 Week 2 Week 3
Week 4
Project manager task
task
task

Project Manager
Project Manager
From: Rob Schneider on
I think all you have to do is display all the subprojects in that Master
Project, then use a filter (on the field(s) you wish to define as dates
for the filter) to limit the tasks. This would be shown in a Gantt
chart with Weeks as the time interval.


--rms

www.rmschneider.com




On 12/05/10 20:25, karens wrote:
> I have a master project with approximately 30 subprojects. Each project has
> a project manager. I want to be able to run a report that shows the project
> managers and the activities that fall under that project manager within a
> certain timeframe. Ultimately, I'd also like to be able to have a graph or
> chart that shows how much % of work the PM has during a time frame. I'm
> fairly new to Project, used to use Primavera. Can anyone help??
> My report would look something like this:
>
> Week 1 Week 2 Week 3
> Week 4
> Project manager task
> task
> task
>
> Project Manager
> Project Manager