From: lk50 on

Hi there,

How do I show resource initials on the gantt chart rather than their
full names?

Many thanks


--
lk50
------------------------------------------------------------------------
lk50's Profile: http://forums.techarena.in/members/87282.htm
View this thread: http://forums.techarena.in/microsoft-project/1293061.htm

http://forums.techarena.in

From: Rob Schneider on
Right mouse click on the Gantt Chart, and pick Bar Styles. Find the row
for task (to which the names are attached). Show the Text tab at
botton, and pick "Resource Initials" instead of "Resource Names". There
is a Help button on that dialog box for more information.


--rms

www.rmschneider.com




On 14/01/10 09:40, lk50 wrote:
> Hi there,
>
> How do I show resource initials on the gantt chart rather than their
> full names?
>
> Many thanks
>
>
From: lk50 on

Thanks for you help on this Rob


--
lk50
------------------------------------------------------------------------
lk50's Profile: http://forums.techarena.in/members/87282.htm
View this thread: http://forums.techarena.in/microsoft-project/1293061.htm

http://forums.techarena.in

From: Trevor Rabey on
Easy.
Format, Bar Styles.
You see a text tab and a bars tab in the lower half.
Text tab.
Choose any field for the right end of the bar, or on top or under or inside.
--
Trevor Rabey
0407213955
61 8 92727485
PERFECT PROJECT PLANNING
www.perfectproject.com.au

"lk50" <lk50.44rxrc(a)DoNotSpam.com> wrote in message
news:lk50.44rxrc(a)DoNotSpam.com...
>
> Hi there,
>
> How do I show resource initials on the gantt chart rather than their
> full names?
>
> Many thanks
>
>
> --
> lk50
> ------------------------------------------------------------------------
> lk50's Profile: http://forums.techarena.in/members/87282.htm
> View this thread: http://forums.techarena.in/microsoft-project/1293061.htm
>
> http://forums.techarena.in
>