From: Prasad on 27 Nov 2009 11:41 On Nov 26, 9:05 pm, Allan <Al...(a)discussions.microsoft.com> wrote: > I would like to Carry a Generic Resource up to the point of actual work then > randomly assign to individual resources. I do not see any problem with this approach as long as each resource has a unique skill. A specific resource can be selected from the group for a task at the starting time of the task using any rational criterion.