From: Strider on 3 Feb 2010 14:23 I have a task with a team of 6 people. each has to devote 30 minutes of effort per day to review project materials ofver a 3 week period. How do I set this up? I'd expect to see a string of 30 minute events over the period in the Gantt view. TIA
From: Dale Howard [MVP] on 3 Feb 2010 15:08 Strider -- Here's one way to handle this: 1. In the Gantt Chart view, enter the task name and then set the Duration to 15d (the 3-week window you mention). 2. Click Window - Split to apply the Task Entry view. 3. In the bottom pane (Task Form), click the Task Type pick list, choose the Fixed Duration item, and then click the OK button to apply this change. 4. In the Resource column in the Task Form, individually select each of your 6 people (do not click the OK button yet). 5. Set the Work value to 7.5h each of the 6 people in the bottom pane. 6. Click the OK button in the Task Form. The 7.5h value in step #5 is 30 minutes per day x 5 days/week x 3 weeks. The system will calculate a Units value of 6% for each resource. This is one way to handle it. Perhaps the others in the group will share their ideas with you as well. Hope this helps. -- Dale A. Howard [MVP] VP of Educational Services msProjectExperts http://www.msprojectexperts.com http://www.projectserverexperts.com "We write the books on Project Server" "Strider" <Strider(a)discussions.microsoft.com> wrote in message news:AE2EBFEE-398E-4116-A35E-E9C97A918620(a)microsoft.com... > I have a task with a team of 6 people. each has to devote 30 minutes of > effort per day to review project materials ofver a 3 week period. How do > I > set this up? I'd expect to see a string of 30 minute events over the > period > in the Gantt view. > > TIA
From: Trevor Rabey on 3 Feb 2010 20:11 You could do this: Duration first, 15 Days Assign the 6 people at 100% Change the Task Type to Fixed Duration. This only needs to be temporary, to protect the duration for what we are about to do next. This could have been done immediately after estimating the duration at 15 days above. I would probably put it back to the default Fixed Units after we are finished here. Switch to the task Usage View. Adjust the timescale zoom to see each day. Enter 0.5 for each day on the grid. There are 6 resources and 15 days so that's 90 cells. Obviously, you would not type 0.5 90 times. It's a snap with copy, paste, fill down (ctrl-c, ctrl-v, ctrl-d). There are other ways. Your 15 day task is probably too long and should be broken down into shorter stages, so you can track it better etc. And 6 people on one task is probably too many. You could go the whole hog and make 90 x 30 minute tasks, then summaries and roll-ups. Perhaps be careful about the use of the word "effort" when you mean Work as defined in MSP, what used to be called "man-hours". -- Trevor Rabey 0407213955 61 8 92727485 PERFECT PROJECT PLANNING www.perfectproject.com.au "Strider" <Strider(a)discussions.microsoft.com> wrote in message news:AE2EBFEE-398E-4116-A35E-E9C97A918620(a)microsoft.com... > > I have a task with a team of 6 people. each has to devote 30 minutes of > effort per day to review project materials ofver a 3 week period. How do > I > set this up? I'd expect to see a string of 30 minute events over the > period > in the Gantt view. > > TIA
From: Jim Aksel on 3 Feb 2010 22:31 Perhaps it does not need to be so difficult. Essentially, you have 3 hours of work per day divided among 6 people (30 minutes each). 30mins/8hours = 6.25% assignment units. Each resource will work 7.5 hours over the course of 15 business days "reveiwing project materials" Type in the task name: Reveiw Project Materials (I am assuming this to be one task, I am not so sure we get much value out of making it more granular than that. After all, are all the other tasks on the schedule broken down into intervals of 30 minute duration with 6 resources assigned? I hope not, that is probably too much detail - IMHO). So, I assume you have a level of effort task. On the menu Window/Split... You now have two windows. In the bottom window, change the task to fixed duration, assign your six resources and make their assignment units 6.25% or make their work 7.5 hours (30 mins/day for 15 days). No need to do both, Project can figure that part out nicely. -- If this post was helpful, please consider rating it. Jim Aksel, MVP Check out my blog for more information: http://www.msprojectblog.com "Strider" wrote: > I have a task with a team of 6 people. each has to devote 30 minutes of > effort per day to review project materials ofver a 3 week period. How do I > set this up? I'd expect to see a string of 30 minute events over the period > in the Gantt view. > > TIA
|
Pages: 1 Prev: www.amiproject.com Next: Weeknumbers |