From: Bjarne Jensen on 4 Feb 2010 05:27 Hi newsgroup, I'm working in Project 2007 PRO. In the normal Gant chart, there are three topline, eg. used for WEEKDAY, DATE and MONTH. You can also select the week number. I would like to have all four information presented in the top of the gant chart. Is that possible? Thanks in advance. / Bjarne
From: Rob Schneider on 4 Feb 2010 06:13 AFAIK, only three tiers available. See Menu: Format/Timescale for setting the tiers. --rms www.rmschneider.com On 04/02/10 10:27, Bjarne Jensen wrote: > Hi newsgroup, > > I'm working in Project 2007 PRO. > > In the normal Gant chart, there are three topline, eg. used for WEEKDAY, > DATE and MONTH. You can also select the week number. I would like to > have all four information presented in the top of the gant chart. Is > that possible? > > Thanks in advance. > > / Bjarne
From: Jim Aksel on 4 Feb 2010 16:26 The horizontal timescale is limited to three lines. It is possible to use Project Day numbering for any value. But you cannot add a fourth line. -- If this post was helpful, please consider rating it. Jim Aksel, MVP Check out my blog for more information: http://www.msprojectblog.com "Bjarne Jensen" wrote: > Hi newsgroup, > > I'm working in Project 2007 PRO. > > In the normal Gant chart, there are three topline, eg. used for WEEKDAY, > DATE and MONTH. You can also select the week number. I would like to have > all four information presented in the top of the gant chart. Is that > possible? > > Thanks in advance. > > / Bjarne >
From: Sai on 4 Feb 2010 23:03 On Feb 4, 3:27 pm, "Bjarne Jensen" <bjarnejen...(a)hotmail.com> wrote: > Hi newsgroup, > > I'm working in Project 2007 PRO. > > In the normal Gant chart, there are three topline, eg. used for WEEKDAY, > DATE and MONTH. You can also select the week number. I would like to have > all four information presented in the top of the gant chart. Is that > possible? > > Thanks in advance. > > / Bjarne No. You can have maximum of three tiers only in timescale - Sai, PMP, PMI-SP, MCT, MCTS http://saipower.wordpress.com
From: Bjarne Jensen on 5 Feb 2010 08:48
Hi all, Thank you all of you - I got the point ;-) /Bjarne "Sai" <sai.nivas.public(a)gmail.com> skrev i meddelelsen news:08a7cee4-ca3c-4a44-bfb5-44037c6db63d(a)o16g2000prh.googlegroups.com... > On Feb 4, 3:27 pm, "Bjarne Jensen" <bjarnejen...(a)hotmail.com> wrote: >> Hi newsgroup, >> >> I'm working in Project 2007 PRO. >> >> In the normal Gant chart, there are three topline, eg. used for WEEKDAY, >> DATE and MONTH. You can also select the week number. I would like to have >> all four information presented in the top of the gant chart. Is that >> possible? >> >> Thanks in advance. >> >> / Bjarne > > No. You can have maximum of three tiers only in timescale > > - Sai, PMP, PMI-SP, MCT, MCTS > http://saipower.wordpress.com |