From: Bjarne Jensen on
Hi newsgroup,

I'm working in Project 2007 PRO.

In the normal Gant chart, there are three topline, eg. used for WEEKDAY,
DATE and MONTH. You can also select the week number. I would like to have
all four information presented in the top of the gant chart. Is that
possible?

Thanks in advance.

/ Bjarne

From: Rob Schneider on
AFAIK, only three tiers available. See Menu: Format/Timescale for
setting the tiers.


--rms

www.rmschneider.com




On 04/02/10 10:27, Bjarne Jensen wrote:
> Hi newsgroup,
>
> I'm working in Project 2007 PRO.
>
> In the normal Gant chart, there are three topline, eg. used for WEEKDAY,
> DATE and MONTH. You can also select the week number. I would like to
> have all four information presented in the top of the gant chart. Is
> that possible?
>
> Thanks in advance.
>
> / Bjarne
From: Jim Aksel on
The horizontal timescale is limited to three lines.

It is possible to use Project Day numbering for any value. But you cannot
add a fourth line.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com



"Bjarne Jensen" wrote:

> Hi newsgroup,
>
> I'm working in Project 2007 PRO.
>
> In the normal Gant chart, there are three topline, eg. used for WEEKDAY,
> DATE and MONTH. You can also select the week number. I would like to have
> all four information presented in the top of the gant chart. Is that
> possible?
>
> Thanks in advance.
>
> / Bjarne
>
From: Sai on
On Feb 4, 3:27 pm, "Bjarne Jensen" <bjarnejen...(a)hotmail.com> wrote:
> Hi newsgroup,
>
> I'm working in Project 2007 PRO.
>
> In the normal Gant chart, there are three topline, eg. used for WEEKDAY,
> DATE and MONTH. You can also select the week number. I would like to have
> all four information presented in the top of the gant chart. Is that
> possible?
>
> Thanks in advance.
>
> / Bjarne

No. You can have maximum of three tiers only in timescale

- Sai, PMP, PMI-SP, MCT, MCTS
http://saipower.wordpress.com
From: Bjarne Jensen on
Hi all,

Thank you all of you - I got the point ;-)

/Bjarne

"Sai" <sai.nivas.public(a)gmail.com> skrev i meddelelsen
news:08a7cee4-ca3c-4a44-bfb5-44037c6db63d(a)o16g2000prh.googlegroups.com...
> On Feb 4, 3:27 pm, "Bjarne Jensen" <bjarnejen...(a)hotmail.com> wrote:
>> Hi newsgroup,
>>
>> I'm working in Project 2007 PRO.
>>
>> In the normal Gant chart, there are three topline, eg. used for WEEKDAY,
>> DATE and MONTH. You can also select the week number. I would like to have
>> all four information presented in the top of the gant chart. Is that
>> possible?
>>
>> Thanks in advance.
>>
>> / Bjarne
>
> No. You can have maximum of three tiers only in timescale
>
> - Sai, PMP, PMI-SP, MCT, MCTS
> http://saipower.wordpress.com