From: PaseEscolar on

How do i protect or block this final date from Gantt????


--
PaseEscolar
------------------------------------------------------------------------
PaseEscolar's Profile: http://forums.techarena.in/members/166005.htm
View this thread: http://forums.techarena.in/microsoft-project/1284687.htm

http://forums.techarena.in

From: Rob Schneider on
Can you please elaborate on what you want? From what "threat" or other
thing are you trying to protect? And what is a "final date gantt"?

There is not special security inside a MPP file. If one has a copy of
the MPP file anyone can change whatever they want. What you instead
need to focus on is securing the source or original MPP file from change
if it other people making changes.

You can set the "official" plan, prior to recording updates/status by
setting a Baseline. Read about Baselines in Project's Help.


--rms

www.rmschneider.com




On 21/12/09 15:51, PaseEscolar wrote:
> How do i protect or block this final date from Gantt????
>
>
From: John on
In article <PaseEscolar.43jyfb(a)DoNotSpam.com>,
PaseEscolar <PaseEscolar.43jyfb(a)DoNotSpam.com> wrote:

> How do i protect or block this final date from Gantt????

PaseEscolar,
What exactly do you mean by "protect" or "block"? If you mean you want
to prevent anyone from making changes, then your only option is to write
protect the whole file. If you mean you want to prevent the date from
moving in a dynamic project, then you can set it as a deadline date,
(i.e. use Deadline field), and manage the project toward that goal.

Remember, NO dates are absolutely fixed. You either meet them or you
don't. As a project manager it is your job to do the best planning and
execution of that plan as is humanly possible. If you miss a critical
date, then hopefully you learned something for the next time. If you
beat the date, then good for you - hopefully you didn't cut corners to
get there. If you make the date exactly then you are either very good or
very lucky.

John
Project MVP