From: DodoMSP on 19 Dec 2009 15:57 Hi, I currently have a Task Usage View that displays information up to 2049. My project end date is 2017. How can I customize the view to only show data up to 2017? I have a lot of blank on the right side and that makes the printout out the view difficult. Thanks DodoMSP
From: Andrew Lavinsky on 19 Dec 2009 16:40 Have you tried clicking in the table on the right, holding down the ctrl key and scrolling with the mouse wheel? The magnifiying glass command will do the same. ....or did I misunderstand your question? - Andrew Lavinsky Blog: http://blogs.catapultsystems.com/epm > Hi, > > I currently have a Task Usage View that displays information up to > 2049. My project end date is 2017. > > How can I customize the view to only show data up to 2017? > I have a lot of blank on the right side and that makes the printout > out the > view difficult. > Thanks > > DodoMSP >
From: JulieS on 19 Dec 2009 17:32 Hello DodoMSP, All views will show up to Dec 31 2049. There is no way to remove the dates past your project end date when scrolling. However, for printing you can control what date range you print through the File > Print command. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "DodoMSP" <DodoMSP(a)discussions.microsoft.com> wrote in message news:9256668B-2161-4456-B3A2-89B416767AC9(a)microsoft.com... > Hi, > > I currently have a Task Usage View that displays information up to > 2049. > My project end date is 2017. > > How can I customize the view to only show data up to 2017? > I have a lot of blank on the right side and that makes the > printout out the > view difficult. > > Thanks > > DodoMSP
|
Pages: 1 Prev: how can i remove microsoft 1.0.3705 Next: How do i block or protect final date gantt?? |