From: Dean C on 4 Mar 2010 12:28 In Project 2007, when you display the Baseline Start field in view with grouping turned on, Baseline Start displays the Maximum Baseline Start of the tasks that form the group, not the minimum. To work around this bug, customize a Start or Date field to equal Baseline Start with Summary calculating rollup minimum.
|