From: Dean C on
In Project 2007, when you display the Baseline Start field in view with
grouping turned on, Baseline Start displays the Maximum Baseline Start of the
tasks that form the group, not the minimum. To work around this bug,
customize a Start or Date field to equal Baseline Start with Summary
calculating rollup minimum.
 | 